Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual 164000639—Rev 03
45
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for the
first time.
Installation Checklist
o
All IBCs are the same model and rating.
o
All packing materials and restraints have been removed from each cabinet.
o
The IBCs are installed on a level floor suitable for computer or electronic equipment.
o
The IBCs are placed in their installed location
o
All conduits and cables are properly routed between the IBCs and the UPS.
o
All power cables are properly sized and terminated.
o
A ground conductor is properly installed.
o
Battery cables are terminated on the positive and negative terminals in the UPS cabinet.
o
Battery Shunt trip and Battery Detect signal wiring is connected from the battery breaker to the UPS.
o
All internal safety shields are installed.
o
Air conditioning equipment is installed and operating correctly.
o
The area around the UPS system is clean and dust-free.
o
Adequate workspace exists around the IBC and other cabinets.
o
Adequate lighting is provided around all IBC and UPS equipment.
o
A 120 Vac service outlet is located within 7.5 meters (25 feet) of the IBC and UPS equipment.
o
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
o
Visit
www.eaton.com/pq/register
to register your new Eaton UPS / Eaton UPS Accessory.