Flexi -3G Installation & Commissioning Manual
Chapter 6. Installation of AC Cables
Document No: - 4493-CM-EN-10989402
Page 59 of 94
Copyright © 2008-2009 Eaton Corporation. All Rights Reserved
1Ø 3Ø
N/A
4 core cable of 10mm² minimum
or
10mm² minimum PVC (80°C minimum)
singles in trucking or conduit.
Table 6-3 PBA-02 Cable Rating
6.5.2. AC Connection Information
Fig. 6-6 PBA-02 AC Rating Information Label
6.5.3. Installing Rectifiers in a PBA-02 System to Balance Phases
In order to provide a balanced load on the incoming AC supply, Install the quantity of rectifiers
required for the Power Supply Unit, with reference to the General Notes for Installing a Rectifier in
section 5.2. on page 49 and according to the table below.
Phase Connected
To
Rectifier Position in
Cabinet from Left to
Right
Installation Sequence
Ø1/Ø2
1
1
Ø2/Ø3 2
2
Ø1/Ø3 3
3
Ø1/Ø2 4
4
Ø2/Ø3 5
5
Ø1/Ø3 6
6
Ø1/Ø2 7
7
Ø2/Ø3 8
8
Ø1/Ø3 9
9
Table 6-4 Installing Rectifiers in a PBA-02 Power Supply Unit