Start-Up
Copyright © 2007-2010 Eaton Corporation. All Rights Reserved.
IPN 997-00012-52D July 2010
35
Step 3 - Repeat for other rectifiers or fit blank panels
If not already fitted, fit rectifier blank panels in any vacant rectifier positions.
Procedure complete
Task 2 - Pre-Power-Up Checklist
Complete the checklist to confirm initial work is complete before progressing further.
All cabling is installed, securely tied and correctly insulated
Ground bonding is correct (see details on page
)
DC battery and load cabling has the correct polarity
A registered electrician or other suitable approved person has checked the integrity of the
installed cabling
All panels are in place and all empty rectifier slots are covered with blanking panels
AC supplementary protector (if fitted) switched off
All dc circuit breakers are switched off and/or fuses removed
AC supply is isolated at each point of isolation leading back to the ac supply point
Batteries are electrically isolated from the dc power system
The site is clean.
Task 3 - Applying AC Power
•
A registered electrician (or suitably qualified person) must check the integrity of the
installed cabling, BEFORE the dc power system is powered up.
1
Switch on the AC supply.
•
All rectifiers start up (after the startup delay).
•
The rectifier alarm LEDs will turn on for a short time.
•
The SC200 or SC100 system controller will turn on (green Power On LED is on) when
the rectifiers start.
•
During start-up of the system controller the rectifier yellow alarm LEDs will flash until
the rectifiers are registered.