UPS installation plan and unpacking
Use the following basic sequence of steps to install the UPS:
1.
Create an installation plan for the UPS system.
2.
Prepare your site for the UPS system.
3.
Inspect and unpack the UPS cabinet.
4.
Unload and install the UPS cabinet and wire the system.
5.
Complete the installation checklist provided in Section 4.2.
6.
Have authorized service personnel perform the preliminary
operational checks and startup.
NOTE: Startup and operational checks for parallel systems or
installations with accessory cabinets must be performed by an
authorized Eaton Customer Service Engineer, or the warranty terms
specified in the Warranty (see Chapter 11) become void. This service is
offered as a part of the sales contract for the UPS. Contact an Eaton
service representative in advance (usually a 2-week notice is required)
to reserve a preferred startup date.
WARNING
Only qualified technicians or electricians are allowed to carry out the
installation. The installation must also be done according to the
applicable safety standards.
Do not open any covers in the UPS. There are no user-serviceable
parts inside the UPS.
The UPS unit is not suitable for IT (Isolated neutral or impedance-
earthed neutral) or corner-earthed power distribution systems.
During installation, make sure that no line input source can accidentally
be connected to the UPS.