Full System Initialization
Once the burner system, MFD, Fan, PDS, and ADC100 have been wired correctly, a full system check is required.
1)
Turn ON main gas supply to appliance.
2)
Press the ON/OFF button on remote to turn ON appliance
3)
Verify, if possible, the fan and MFD has been activated.
4)
Once draft is proven by the PDS, the ADC100 sends a signal to burner control module to allow for burner
operation.
5)
The burner pilot will begin sparking.
a.
If pilot does not light after 30 seconds, turn off appliance for 30 seconds and retry step 2.
b.
It may take several attempts to purge out all the air in pilot tube.
6)
Once the pilot is ignited, the main burner valve will turn on within 7 seconds.
7)
The burner should ignite, and the flames should travel along the length of the burner.
8)
Initially, the flames will have a bluish appearance and will gradually become more yellow as appliance heats up.
9)
After a few minutes, shut off burner by pressing OFF on the remote, allow the burner to cool to the touch.
10)
Glass media can be spread evenly across the entire the length burner.
DO NOT
leave excessive amounts of media
directly on top of burner ports.
DO NOT
obstruct pilot assembly with glass media.
11)
Restart sequence on step 2.
12)
Observe flame pattern. The fan speed control can be adjusted to minimize erratic flame patterns. The fan speed
control voltage shall not be less than 90 VAC as measured with voltage meter at junction nearest fan.
NOTE:
The fan speed control should only be used for initialization set up and should only be altered by
qualified professional.
13)
Once a satisfactory flame appearance has been achieved, system is complete.