5. Connect the solenoid valve wire and motor wire.
Step 12: Install lifting arms.
Connect the lifting arm and the carriage. The arm pin shafts must be greased at the installation Ensure the arm lock can engage and
release effectively. .
Attention: Install Lifting arms and fix feet protection bars ONLY after the complete assembly has been erected and anchored.
Step 13: Fill with hydraulic oil.
CLEAN AND FRESH OIL ONLY. DON’T FILL THE TANK COMPLETELY FULL.
Lift must be fully lowered before changing or adding hydraulic oil
Prepare 10 liters of anti-abrasion hydraulic oil. The level of oil shall reach the tippets volume mark of the tank.
Add more oil after running the lift for several cycles until the lift can rise to the maximum lifting height.
It is suggested to use HM NO.46 hydraulic oil. When average temperature of the location is below 10
℃
, use HM NO.32 hydraulic oil.
Change the oil 6 months after initial use and change once per year thereafter.
1.Power unit
2.Motor wire
3.Solenoid valve wire
4.Control box
5.Power supply wire
1.Pulling rod
2.Arm locking unit
1.Pin shaft
2.Long arm
3.Short arm