Step1
System outage
Ensure that the battery is in a shutdown state
Step 2
Mechanical
installation
1. Hanger mounting
2.Equipment installation
Step3
Electrical
installation
1. Connect the ground cable
2 Electrical installation
3.Connect inverter
4.Communication interface connection
3.2.1 Floor installation
When the battery system is placed directly on the ground, a fixed support must be used
to fix the top of the battery box with the wall.
3
.
4 holes with diameter of 10mm shall
be opened on the wall with electric
drill according to the marked position,
and the hole depth shall be greater
than 70mm to fit the expansion bolts
of M6.
1
.
Use the positioning cardboard
provided with the goods to draw
the screw hole positions on the
wall, as shown in the four holes
on the left.
2
.
The bottom of board must be good
connection with the ground level