DUALSUN 300M-60-0BBP Скачать руководство пользователя страница 4

 
 

4 / 17     

Installation Manual for DualSun PV Modules

 

 

H, M or L (H means the highest current level). The best practice is to install modules with the 

same current level (such as H) in one strand in the process of installation.   

3.  Serial  No.:  Each  module  has  a  unique  serial  number  which  is  solidified  inside  the  module 

permanently and it can be seen from front top of the module. Each serial number is put in before 

laminating  of  the  module.  In  addition,  you  can  find  the  same  serial  number  on  the  module 

nameplate.   

 

Frame 

glass 

EVA 

cell 

backsheet 

silicon 

Connecting 

box 

Nameplate 

Cables 

10 

Connector 

11 

Mounting 

hole 

12 

Grounding 

hole 

13 

Leakage 

hole 

14 

shape code

 

 

 

 

 

Figure 1

Module Section Structure and Components

 

3.2 

Regular safety 

DualSun  module  is  considered  to  be  in  compliance  with  IEC61730  only  when  the  module  is 

mounted in the manner specified by the mounting instructions below. 

When the module is installed on roof, it is necessary to take the overall fire rating of the finished 

structure as well as later overall maintenance into account. The roofing PV system shall be installed 

after assessment by construction experts or engineers and with official analysis results for the entire 

structure.  It  shall  be  proved  capable  of  supporting  extra  system  bracket  pressure,  including  PV 

module weight.   

For your safety, please do not work on the roof without safety protective measures which include 

but not limited to fall protection, ladder or stair and personal protective articles.   

For your safety, please do not install or handle modules in unfavorable conditions including but 

not limited to strong wind or gust, damp or sandy roofs.   

Содержание 300M-60-0BBP

Страница 1: ...tions in this guide and local regulations Installation of modules requires professional skills and knowledge and is to be carried out by qualified personnel Please read this manual carefully before in...

Страница 2: ...lection of tilt angles 7 5 Mechanical installation 7 5 1 Regular requirements 7 5 2 Way of installation 8 6 Electric installation 11 6 1 Electric performance 11 6 2 Cables and connecting lines 13 6 3...

Страница 3: ...install modules as per requirements set forth in this manual the quality warranty provided for customers during sales will become invalid In addition suggestions in this manual are to improve safety...

Страница 4: ...Regular safety DualSun module is considered to be in compliance with IEC61730 only when the module is mounted in the manner specified by the mounting instructions below When the module is installed o...

Страница 5: ...cles and isolate modules from the circuit Working is only allowed in dry conditions by means of dry tools Do not operate when modules are wet unless you wear the proper electric shock protection devic...

Страница 6: ...oof Please refer to the IEC61730 1 Clause 12 4 a Fire resistant rating of roof covering Class C b Module installation Angle 22 5 4 Installation conditions 4 1 Installation site and working environment...

Страница 7: ...print on the glass due to long time of water ponding which may further affect module appearance and performance 5 Mechanical installation 5 1 Regular requirements Make sure that module installation mo...

Страница 8: ...allation as described in this manual load for the test load Note on the basis of IEC61215 2016 installation requirements when computing the corresponding maximum design load need to consider the safet...

Страница 9: ...odules on the bracket by metal clamp The following clamps or those clamps recognized by module system installer are recommended Width no less than 40mm Thickness no less than 4mm Material aluminum all...

Страница 10: ...e modules have been evaluated by TUV according to IEC61215 for a maximum testing loadof below112 78lb ft2 5400Pa 2400pa design load 3600pa 1600pa 1 5 ML Frame Way of Installation 5400pa 2400pa Mountin...

Страница 11: ...testing conditions of irradiance of 1000 W m2 cell temperature of 25 and air mass of AM1 5 Under normal conditions a photovoltaic module is likely to experience conditions that produce more current an...

Страница 12: ...nd parallel connection circuit diagram The number of modules in series connection in each strand shall be calculated as per requirements The open circuit voltage value under the expected lowest temper...

Страница 13: ...is suitable for applications where wiring is exposed to the direct sunlight We require that all wiring and electrical connections comply with the appropriate National Electrical Code When cables are...

Страница 14: ...otect modules from lightning and static electricity damage the module frame shall be grounded The grounding device shall be in full contact with inner side of the aluminum alloy and penetrate the fram...

Страница 15: ...mounting holes Mounting holes on modules that are not occupied can be used for installing grounding devices 1 Align grounding clamp to the frame mounting hole Use grounding bolt to go through the gro...

Страница 16: ...e degree of influence is determined by transparency of wastes Small amounts of dust will affect sunlight strength and evenness but are not dangerous and power will not be reduced remarkably in general...

Страница 17: ...d to carry out a preventive inspection once every 6 month 1 Check connector sealing and cable connection solidness 2 Check whether sealant of the terminal box is cracking with gap Module DualSun 300M...