ENGINE GENERATOR SET MOUNTING

The unit’s main frame should be bolted solid to a four to
six inch thick cement pad.  The engine-generator is
mounted on a sub-frame which is isolated with special
shock mounts on the main frame.  This allows the engine-
generator to vibrate without affecting the control panel on
the main frame.

Do not install any shock mounts between the  base

frame and the concrete pad.  Engine vibration will be
transmitted to the control panel causing erroneous start/
stop cycles and premature control failure.

The unit should be mounted to allow for ample working

room around it.  A general rule to follow is three (3) feet
clearance on all sides.  NFPA 37 requires at least 3 feet
clearance  from any structures having combustible
adjacent walls and 5 feet from openings in walls.  Particu-
lar attention should be paid to the direction of the hot air
discharge and exhaust discharge.  Unit location should be
such that these discharges are not allowed to be drawn
back in through an open window or door.

FUEL INSTALLATION

The fuel supply should be as close as possible to the

engine.  This will reduce the installation cost of fuel runs.
The information in this manual is offered to assist you in
providing the proper fuel for your engine. However, this
information is only provided to inform you of the engine’s
requirements and assist in making you aware of the
decisions you must make.  In no case should the instruc-
tions or information provided be interpreted to conflict with
any local, state or national codes.  If in doubt, always
consult your local fire marshal or gas supplier.

    *************

*****  WARNING  ****
    *************
FIRE HAZARD  - All fuel runs should be installed by a
licensed fuel supplier.

To connect the fuel line, locate the 3/4 inch NPT fuel

inlet fitting on the side of the enclosure.  This inlet is
shipped with a plastic cap plug installed to insure the fuel
system stays clean.

    *************

*****  WARNING  ****
    *************
FIRE HAZARD - DO NOT OVERTIGHTEN THE FUEL
LINE. THIS IS A TAPERED FITTING, OVERTIGHTENING
WILL CAUSE THE FITTING TO CRACK AND LEAK
FUEL.

For all vapor fuel systems the delivery pressure of the

fuel to the fuel solenoid on the unit must be four to six
ounces psi (per square inch) or 7 to 11 inches W.C.
(Water column). These fuel pressures are critical; failure
to provide the proper fuel pressure can cause many
problems ranging from a unit that will not start to causing
damage to the fuel system

.

INSTALLING THE FUEL LINE

** NOTICE **

The engine generator sets are properly adjusted before
they leave the factory.  A tag is attached to the unit that
specifies the fuel, natural gas (NG) or propane vapor (LP)
that the unit was set up and tested on.

Line Size

Unit location will determine the size of fuel line that is

required to supply the engine with a constant fuel pres-
sure and volume.  Refer to the tables below for fuel line
size, fuel consumption and recommended tank size.  For
distances of 50 feet and over, a two regulator fuel system
is recommended.  This is accomplished by installing a
primary regulator at the tank which will reduce the tank
pressure down to 10 to 15 lbs.  A secondary regulator is
installed to further reduce the fuel pressure to the required
four (4) to six (6) oz operating pressure.  This secondary
regulator must be at least 10 feet from the engine genera-
tor set, any closer installation will require a larger line be
installed to provide a fuel reservoir.   This is also true for
the single dual stage regulators, it should also be mini-
mum of 10 feet from the unit.   If this is not done the
demand regulator on the unit and the pressure regulator
in the fuel line will interfere with each other.

When the two (2) stage regulator system is used, a fuel

line size of 1/2 to 5/8 inch is generally adequate for
distances up to 300 feet from the primary to the second-
ary regulator.  (Consult your local fuel supplier for your
exact requirements.) The appropriate line size from the
table below is then installed from the secondary regulator
to the generator set.

Содержание WINCO PSS15B2W/A

Страница 1: ...PACKAGED STANDBY SYSTEM PSS15B2W A INSTALLATION AND OPERATORS MANUAL Engine Generator Set...

Страница 2: ...rication 6 Battery Installation 6 Connecting Battery Charger 6 TRANSFER SWITCH INSTALLATION 6 AC Electrical Connections 7 DC Electrical Connections 8 INITIAL START UP 8 TROUBLESHOOTING INFORMATION 9 W...

Страница 3: ...ut of reach of children c Do not smoke or use open flame near the generator set or fuel tank d Keep a fire extinguisher nearby and know its proper use Fire extinguishers rated ABC by NFPA are appropri...

Страница 4: ...UNIT LINE SIDE GENERATOR CONTACTOR SIDE CONTACTOR PSS15B2W A 100AMPS 60 AMPS UL Automatic Transfer Switch Sizes UNIT LINE SIDE GENERATOR CONTACTOR SIDE CONTACTOR PSS15B2W A 100 AMPS 100 AMPS 200 AMPS...

Страница 5: ...rrier for claim procedures Be sure to retain the packaging material for carrier inspection Concealed Damage is understood to mean damage to the contents of a package which is not evident at the time o...

Страница 6: ...stays clean WARNING FIRE HAZARD DO NOT OVERTIGHTEN THE FUEL LINE THIS IS A TAPERED FITTING OVERTIGHTENING WILL CAUSE THE FITTING TO CRACK AND LEAK FUEL For all vapor fuel systems the delivery pressure...

Страница 7: ...n inches of water column The second is with a pressure gauge calibrated in ounces per square inch Reference numbers 1 through 3 in the block diagrams above are system parts supplied by customer Refere...

Страница 8: ...battery terminal is connected to the negative cable ground from the engine generator assembly All connections must be clean and tight Check the electrolyte fluid in the battery periodically to be sure...

Страница 9: ...ion panel should contain your only neutral to ground bond All power leads from the generator to the A T S must be sized to handle rated generator output amperage at a minimum the type of wire you use...

Страница 10: ...anded wire should be used These wires will be labeled Bat and Start The control wires will be connected as follows in the generator control terminal box ATS Panel Generator Control Panel Start 1 to Wi...

Страница 11: ...s you will have to fail the incoming line power to the A T S panel All the loads connected to the A T S should now be dead The engine generator set will go into a 3 to 10 second start delay At the end...

Страница 12: ...be 3600 RPM 9 AC short on output leads PREVENTIVE MAINTENANCE Reasonable care in preventive maintenance will insure high reliability and a long life for the engine generator set and the Automatic Tra...

Страница 13: ...PAGE 11 4190 00 60706 169 AC AND DC GENERATOR WIRING DIAGRAM...

Страница 14: ...PAGE 12 60706 169 4190 00 AC AND DC GENERATOR SCHEMATIC...

Страница 15: ...PAGE 13 4190 00 60706 169 GENERATOR LAYOUT...

Страница 16: ...ility and fitness for a particular purpose are limited to 12 months from date of purchase In no event is WINCO liable for incidental or consequential damages Note Some states do not allow limitation o...

Отзывы: