A S S E M B L Y I N S T R U C T I O N S S U N L A K E - O V A L - P A G E 6
EXPLODED SIDE SECTION
Legend for Figure A
11/a/b = Bottom rail
16 = Screws #10 x 1/2"
34 = Antiskid plate
35 = Top ground support
36 = Vertical base
37 = Pressure pad
38 = Vertical pressure pad
39 = Rail connector
40 = Screws #12 x 3/4"
41 = Screws 3/8-16 x 3-1/2"
42 = Screws 3/8-16
43 = Screws 1/4-20 x 1/2"
44 = Screws 1/4-20
45 = Screws #10 x 3/8"
46 = Side support
INSTALL CONCRETE BLOCKS
Step 5
Place two concrete blocks into the excavations and
place the assembled side supports into each trench
perpendicular, so that the front side of the side support
is situated to the tautly wire
.
POSITION SIDE VERTICAL SHIMS
(WITHOUT PROTRUDING HORIZONTAL
BEAM)
Step 5a
Place the horizontal beams two degrees tilted in the
ground. The side supports will stand straight again by
the pressure of the water.
Figure A
side support
assembly
string line
skid
plate
concrete block
horizontal
beam
level
Fill with
concrete
slope
side support assembly
fill with
concrete
firm
undisturbed
earth
level
slope downward
concrete blocks
square wood of 2 cm