Perform functional check of high voltage
Personnel:
Operator
+ additional qualification high tension
technology
+ additional qualification explosion pro-
tection
Protective equipment:
Anti-Static Safety Boots
Protective workwear
Eye protection
Respiratory protection device
Use ear protection
Requirements:
The connection cable, the compressed
air hose and the material supply were
assembled
Fig. 14: Open ball valve
1. Open ball valve (1).
Fig. 15: Switch on electrostatic controller
2. Switch on the electrostatic controller (2).
Fig. 16: “H. V.” indicator light
3. Pull the trigger of the spray gun.
ð
The “H. V.” indicator light (3) on the
electrostatic controller lights up green.
The “H. V.” indicator light on the spray
gun lights up red.
4. Switch off the electrostatic controller (2).
Commissioning
11/2019
EcoGun AS MAN EC - MSG00022EN
12/52