COMMISSIONING
Upon receipt of the unit, and prior to putting it into service, it is
important to adhere strictly to the instructions given below in
PRIOR TO
STARTING.
Ensure that the operator reads and
understands
the decals and
consults the manuals before maintenance or operation.
Ensure that the position of the
emergency stop
device is known and
recognised by its markings. Ensure that it is functioning correctly and
that the method of operation is known.
Running gear drawbar
−
Machines are shipped to some areas with
the drawbar removed. Fitting involves four nuts / bolts to secure the
drawbar to the axle and two bolts to fit the drawbar to the front of the
machine with the saddle and spacer block.
Support the front of the machine, fit the wheel chocks to stop the
machine moving and attach the drawbar. Refer to the torque value table
in the
MAINTENANCE
section of this manual for the correct torque
values.
CAUTION
:
This is a safety critical procedure. Double check the torque settings
after assembly
Fit the propstand and coupling. Remove the supports and set the
machine level.
Before towing the unit, ensure that the tyre pressures are correct
(refer to the
GENERAL INFORMATION
section of this manual) and
that the handbrake is functioning correctly (refer to the
MAINTENANCE
section of this manual). Before towing the unit during
the hours of darkness, ensure that the lights are functioning correctly
(where fitted).
Ensure that all transport and packing materials are discarded.
Ensure that the correct fork lift truck slots or marked lifting / tie down
points are used whenever the machine is lifted or transported.
When selecting the working position of the machine ensure that
there is sufficient clearance for ventilation and exhaust requirements,
observing any specified minimum dimensions (to walls, floors etc.).
Adequate clearance needs to be allowed around and above the
machine to permit safe access for specified maintenance tasks.
Ensure that the machine is positioned securely and on a stable
foundation. Any risk of movement should be removed by suitable
means, especially to avoid strain on any rigid discharge piping.
Attach the battery cables to the battery(s) ensuring that they are
tightened securely
.
Attach the negative cable before attaching the
positive cable.
SET
−
UP (PRIOR TO RAISING TOWER)
1.
Make sure unit is detached from towing vehicle.
2.
Make sure parking brake is correctly engaged.
3.
Inspect cables. Cables should not be frayed, cut, abraded, or
otherwise damaged. Replace damaged cables.
4.
Check hydraulic oil level. Fill if necessary / as required.
5.
Ensure no obstruction is overhaed within 15 meters.
6.
Be sure lamps are secure on cross bar and aim as desired.
7.
Extend all outriggers fully and insert locking pins fully. Ensure
drawbar jack and all outrigger and/or jacks are firmly in contact
with ground.
8.
Level unit using jacks and bubble level indicator.
9.
Jacks must support entire unit weight (tyres off the ground).
BEFORE STARTING THE ENGINE
Before starting the engine, carry out the following checks:
1.
Engine oil level: Add as required.
2.
Engine coolant level: Add as required.
3.
Fuel filter: Drain any accumulation of water. Clean or replace
element as required.
4.
Air cleaner service indicator (if equipped): Service when showing
“red”.
5.
Fuel level in tank: Fill, using CLEAN DIESEL fuel, at the end of the
day to minimize condensation.
6.
Battery: Keep terminals clean and lightly greased.
7.
Engine belts and hoses: Check for proper fit and/or damage.
Service as required.
8.
Air Vents/Grilles: Both engine radiator and generator cooling air.
Check for obstructions (leaves, paper, etc.).
9.
Visual inspection: Check for excessive fluid leaks, evidence of
arcing around control panel, loose wire
−
routing clamps, etc.
CAUTION:
Call a qualified person to make electrical repairs
.
Содержание LIGHTSOURCE V9
Страница 3: ......
Страница 4: ......
Страница 18: ...GENERAL INFORMATION 14 LIGHTSOURCE V9 FIXED HEIGHT RUNNING GEAR VARIABLE HEIGHT RUNNING GEAR...
Страница 33: ...MAINTENANCE 29 LIGHTSOURCE V9...
Страница 34: ...ELECTRICAL SYSTEM 30 LIGHTSOURCE V9 SCHEMATIC DIAGRAM FOR AC ELECTRICAL HARNESS...
Страница 35: ...ELECTRICAL SYSTEM 31 LIGHTSOURCE V9 SCHEMATIC DIAGRAM FOR AC ELECTRICAL HARNESS...
Страница 36: ...ELECTRICAL SYSTEM 32 LIGHTSOURCE V9 SCHEMATIC DIAGRAM FOR AC ELECTRICAL HARNESS...
Страница 38: ...ELECTRICAL SYSTEM 34 LIGHTSOURCE V9 SCHEMATIC DIAGRAM FOR DC ELECTRICAL HARNESS...
Страница 64: ......
Страница 65: ......
Страница 66: ......