![Doka Platform SCP Скачать руководство пользователя страница 151](http://html.mh-extra.com/html/doka/platform-scp/platform-scp_original-operating-instructions-instructions-for-assembly-and-use_2516579151.webp)
Original Operating Instructions
Platform SCP
Start-up phases – Lifting unit attached on one side
151
999805802 - 03/2016
2nd casting section
➤
Remove the service towers from the outsides.
➤
Apply concrete release agent and set up one side of
the formwork.
➤
Adjust the formwork.
➤
Mount the positioning-points.
➤
Mount the 'Boxes for latch'.
➤
Place the reinforcement.
➤
Close the formwork and tie it.
➤
Pour the 2nd section.
➤
Open the formwork.
➤
Clean the formwork.
98058-458-01
Содержание Platform SCP
Страница 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Страница 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Страница 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Страница 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Страница 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...