background image

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Doc # INT-100132-001

Part No. 191556 Rev. 4  

DITEK Technical Support Available 24/7

   1-888-472-6100 www.ditekcorp.com

       

DITEK Corporation

ONE DITEK CENTER

1720 Starkey Road

Largo, FL 33771

INSTALLATION

This Surge Protective Device (SPD) is a high performance device, designed to provide protection

for sensitive electronic loads connected to communication loop circuits that have been isolated 

from the public switched telephone network or where the SPD is directly connected to the 

electronic device. Maximum protection will only be achieved if the SPD is properly installed. 

Please read and follow the installation instructions carefully.

NOTICE:

 This SPD should be installed and grounded, by a licensed contractor, per the applicable

requirements of the NEC and the following instructions. These devices are only to be employed on

communication loop circuits which have been isolated from the Public Switched Telephone Network.

APPLICATION

DTK-MB10

 base can be installed inside a 4”x4” electrical boxes and other locations where there is a space 

constraint. This base is available as a 1 up array (standard) or 2 through 5 up array for multiple pair 

terminations at one point of use. Specify DTK-2MB, 3MB, 4MB or 5MB for 2 through 5 up arrays.

DTK-2MHLPxxFWB

 surge module is for hardwired series installations for voltages ranging from 5-75 Volts 

on circuits that operate at less than 1 Amp.

DTK-2MHLPxxBWB

 surge module is for hardwired series installations for voltages ranging from 5-75 Volts 

on circuits that operate at less than 5 Amps.

DTK-2MHTP

 surge module is for hardwired series installations for dialer circuits and POTS lines for 

communication circuits.

INSTRUCTIONS:

Caution

: Measure all voltages to insure applied voltage does not exceed the voltage rating of the unit. 

Improper installation voids the warranty.

MB BASE INSTALLATION

  1. Turn off the power at the circuit to be protected before beginning installation.

  2. Securely mount the snap track between the field wiring and your equipment to be protected. Use the two #8 screws 

      provided to fasten the snap track.

  3. Connect ground to the ground terminal using a minimum of 14 AWG wire, make this conductor as short as possible.

Ground Resistance Rule: 

Max ground resistance is 25 Ohms, 5 Ohms or less is optimum.

This cannot be an assumed value and must be measured to assure proper grounding.

  4. Connect the supply/field wiring to the 

UNPROTECTED

 side of the  MB base. Connect the 1st pair to 

      position 1+ and 1- , than the 2nd pair to position 2+ and 2-.

  5. Connect the equipment wiring to the 

PROTECTED

 side of the MB base. Connect the 1st pair to 

      position 1+ and 1- , than the 2nd pair to position 2+ and 2-.

  6. Make sure the 

UNPROTECTED

 supply/field wiring and 

PROTECTED

 equipment wiring conductors do not occupy 

      the same space or conduits.

  7. Make sure the wire distance from the base to protected equipment is about 3’ of conductor length. This can be a 

      coiled service loop if necessary.

  

MODULE INSTALLATION

      

Insert the module into the base making sure the polarizing keys in the block are aligned with the notches cut into 

       the edge card  printed circuit board.

  8. After all connections have been made and no hazards exist, restore power.

Drawn By: RMitchell 3-3-11

Revised By: RMitchell 6-14-16

SUPPLY WIRING

or FIELD WIRING

   GROUNDING

  #14AWG MIN.

Pair 1

Pair 2

GND

EQUIPMENT

Pair 1

Pair 2

ALLOW FOR 3’ OF CONDUCTOR LENGTH 

BETWEEN BASE AND PROTECTED EQUIPMENT

DTK-2MHLP BASE

EQUIPMENT WIRING

3’ SERVICE LOOP

            INSTALL INSTRUCTIONS

    DTK-2MHLPxxFWB Series, DTK-2MHLPxxBWB Series,

DTK-2MHTPWB, MB10, 2MB-5MB,  and DTK-2MHLP Module

Отзывы: