6 TESTING
6.1 GENERAL
NOTE: All field wiring must be tested before proceeding to the next step. If the wiring has
not been tested, refer to
Section 2.3., FIELD WIRING
for instructions.
Attach one pair of zone wires at a time to the control panel and activate an initiating device
to test
“ZONE ALARM”. Then proceed to the last device of each zone and open the
circuit to test “ZONE TROUBLE”.
6.2 ACCEPTANCE TESTING
Use Table 6.1 to test all alarm and trouble initiating devices for each zone.
All system functions should be tested based on a period indicated by the NFPA guideline.
In no event shall this period exceed once every three months to insure proper system
operation. If any malfunctions occur, contact your local authorized DIGITIZE, INC.
distributor for qualified service.
Содержание DGM-32/64
Страница 4: ......
Страница 6: ......
Страница 10: ......
Страница 16: ...DGM INSTALLATION AND MAINTENANCE MANUAL 6 700135 0000 Rev O Figure 1 1 DGM 32 64 and DGM 32 64 RF...
Страница 18: ...DGM INSTALLATION AND MAINTENANCE MANUAL 8 700135 0000 Rev O...
Страница 56: ...DGM INSTALLATION AND MAINTENANCE MANUAL 46 700135 0000 Rev O...