- 31 -
Time of use:
it is used to program when to use grid or
generator to charge the ba�ery, and when to discharge
the ba�ery to power the load. Only �ck "Time Of Use"
then the follow items (Grid, charge, �me, power etc.)
will take effect.
Note:
when in selling first mode and click �me of use,
the ba�ery power can be sold into grid.
Grid charge:
u�lize grid to charge the ba�ery in a �me
period.
Gen charge:
u�lize diesel generator to charge the ba�ery
in a �me period.
Time:
real �me, range of 01:00-24:00.
Power:
Max. discharge power of ba�ery allowed.
Ba�(V or SOC %):
ba�ery SOC % or voltage at when the
ac�on is to happen.
Time Of Use
Time
System Work Mode
Batt
Grid
Charge Gen
01:00
05:00
09:00
13:00
17:00
21:00
5:00
9:00
13:00
17:00
21:00
01:00
Power
8000
8000
8000
8000
8000
8000
49.0V
50.2V
50.9V
51.4V
47.1V
49.0V
Work
Mode2
During 01:00-05:00, when ba�ery SOC is lower than 80%, it will
use grid to charge the ba�ery un�l ba�ery SOC reaches 80%.
During 05:00-08:00 and 08:00-10:00, when ba�ery SOC is higher
than 40%, hybrid inverter will discharge the ba�ery un�l the SOC
reaches 40%.
During 10:00-15:00, when ba�ery SOC is higher than 80%, hybrid
inverter will discharge the ba�ery un�l the SOC reaches 80%.
During 15:00-18:00, when ba�ery SOC is higher than 40%, hybrid
inverter will discharge the ba�ery un�l the SOC reaches 40%.
During 18:00-01:00, when ba�ery SOC is higher than 35%, hybrid
inverter will discharge the ba�ery un�l the SOC reaches 35%.
Time Of Use
Time
System Work Mode
Batt
Grid
Charge Gen
01:00
05:00
08:00
10:00
15:00
18:00
5:00
8:00
10:00
15:00
18:00
01:00
Power
8000
8000
8000
8000
8000
8000
80%
40%
40%
80%
40%
35%
Work
Mode2
For example:
Solar Sell:
“Solar sell” is for Zero export to load or Zero export to CT: when this item is ac�ve, the surplus
energy can be sold back to grid. When it is ac�ve, PV Power source priority usage is as follows: load
consump�on and charge ba�ery and feed into grid.
Max. sell power:
Allowed the maximum output power to flow to grid
.
Zero-export Power:
for zero-export mode, it tells the grid output power. Recommend to set it as 20-100W
to ensure the hybrid inverter won' t feed power to grid.
Energy Pa�ern:
PV Power source priority.
Ba� First:
PV power is firstly used to charge the ba�ery and then used to power the load. If PV power is
insufficient, grid will make supplement for ba�ery and load simultaneously.
Load First:
PV power is firstly used to power the load and then used to charge the ba�ery. If PV power is
insufficient, grid will make supplement for ba�ery and load simultaneously.
Max Solar Power:
allowed the maximum DC input power
.
Grid Peak-shaving:
when it is ac�ve, grid output power will be limited within the set value. If the load
power exceeds the allowed value, it will take PV energy and ba�ery as supplement. If s�ll can’t meet the
load requirement, grid power will increase to meet the load needs.
Содержание SUN 5K-SG01LP1-US
Страница 1: ...Hybrid Inverter User Manual R ...
Страница 12: ...3 3 2 Ba ery temperature connec on 1 2 Temp CT 10 ...