Figure 106. Installing power interposer board
Next steps
1. Connect all the cables to the PIB.
2.
.
3. Install the
.
4. Place the system into the rack. For more information, see the
Rail Installation Guide
5.
6. Install the
.
7. Follow the procedure listed in
After working inside your system
System board
Removing the system board
Prerequisites
CAUTION:
If you are using the Trusted Platform Module (TPM) with an encryption key, you may be prompted to create
a recovery key during program or System Setup. Be sure to create and safely store this recovery key. If you replace this
system board, you must supply the recovery key when you restart your system or program before you can access the
encrypted data on your drives.
CAUTION:
Do not attempt to remove the TPM plug-in module from the system board. Once the TPM plug-in module is
installed, it is cryptographically bound to that specific system board. Any attempt to remove an installed TPM plug-in
module breaks the cryptographic binding, and it cannot be re-installed or installed on another system board.
1. Follow the safety guidelines listed in
2. Power off the system and all attached peripherals.
3. Disconnect the system from the electrical outlet, and disconnect the peripherals.
4.
5. Remove the
6. Remove the system from the rack and place it on an ESD work bench. For more information, see the
Rail Installation Guide
at
7.
.
116