5
300001069-001-G - 22/02/06
BH 150
Installation
Installation must be carried out in accordance with the
prevailing regulations, the codes of practice and the
recommendations in these instructions.
1 Assembly of the calorifier with an ELITEC DTG 130
The BH 150 calorifier is designed to be connected to an
ELITEC DTG 130 boiler and perfectly matches the esthetic of this
boiler.
The boiler can be installed:
- either to the side of the calorifier (left or right)
- or on the calorifier (in this case, you must use the stiffening kit
package EA 82, delivered as an option, and respect the assembly
instructions which accompany it).
2 Levelling
Leveling is done using the adjustable feet located on the base of the
calorifier
To make the adjustment, take the load off the foot to be
adjusted using a lever.
(1)
Adjustable feet
:
Basic dimension 10 mm
adjustment possible: 10 à 22 mm
8952N125
(1)
10 mm