05721-1098 <90-00050>

computer to one of the LSO ports. Do a command for the LSO loca-

tion and receive the COMPLD message. This is the check for the

self-healing of the system for a East to West failure.

N.

Reconnect the East Receive fiber and disconnect the West receive

fiber. MAT alarm Point 3 clears. Points 6 and 9 on the MAT module

(Shelf C Slot 13), relay B on the MAT, and relay modules 10A and

11A will all come on or energize. Do a command for a LSO and

receive the COMPLD message. This is  the check for the self-heal-

ing of the system for a West to East failure.

O.

Restore the fiber equipment. All alarms on the local MAT turn off.

At a LSO location, completely shut down the East or West terminal

by removing the receive and transmit fibers in one direction or one

of the connections from he fiber terminal to the DSM assembly. At

the Service Node, MAT alarm points 3, 6 and 9 will operate as well

as relay modules 10A through 13A, and 10B through 13B. (Points 1

or 4 will also turn on if the LSO is the first one from the Service

Node). Check the communications to each LSO on either side of the

LSO that you put in failure, by sending a TL1 command to every

LSO. After checking that the system is working, restore the LSO

that had been placed in the failure mode. This is a check for self-

healing on a complete failure in both directions at a given location.

P.

The 46017 will put out an audible alarm signal whenever there is a

MAT alarm at any location. Disable the audible device with the

lower ACO switch on the module.

Q.

After all ports have been checked out and the connectons are made

to the transport channels, (such as Datakit or Dantel's 46095 X.25

module), have the Alarm Center issue commands to every LSO.

R.

This completes the testing procedure.

INSTALLATION

Содержание A18-05721 Series

Страница 1: ...charge safety precautions refer to BellcoreTM Technical Reference TR NWT 000870 Copyright 1998 by Dantel Inc Dantel is a registered trademark of Dantel Inc ISO 9001 Registered Printed in the U S A INS...

Страница 2: ...Data Port Module The Controller Module is used to interface the 64Kb channel using a RS 422 interface and to interface the Data Port Modules Each Controller can accommodate up to 8 Data Port Modules E...

Страница 3: ...to make a self healing system with two RS 232 ASCII ports at every LSO and one Alarm channel that is common to all LSO locations Each Channel will terminate at the Service Node on DB25 connectors conf...

Страница 4: ...1098 90 00050 FIG 2 REAR VIEW 05721 SYSTEM NOTE For a larger more detailed drawing of the above please refer to Sheet 9 of the A18 05721 XX Block Diagram GENERAL DESCRIPTION SHELF A SHELF A SHELF B SH...

Страница 5: ...NOTE For a larger more detailed drawing of the above please refer to Sheet 9 of the A18 05721 XX Block Diagram GENERAL DESCRIPTION SYSTEM SIDE VIEW REAR PANEL ASSEMBLY REAR PANEL ASSEMBLY REAR PANEL A...

Страница 6: ...IPTION The Service Node location can send or receive data from either direction Refer to Fig 4 The data to and from the East Port modules is opened if there is no faults on the system An RS 232 signal...

Страница 7: ...elays 12A 13A operate and transmission path reverses If there is a failure in both directions all relays operate Transmission and reception will go both directions If the system is back to normal all...

Страница 8: ...Every LSO to the East of the break would now transmit data from the West to the East direction and the LSOs would receive from the East to West direction There would be no conflict of data because of...

Страница 9: ...N INSTALLATION TURN UP PROCEDURE The following is a step by step procedure for turning up the shelf after it has been mounted in an equipment rack and all wiring has been completed STEP 1 MODULE INFOR...

Страница 10: ...FIG 5 46112 DSM DATA CONTROLLER MODULE STRAP LOCATION INSTALLATION Terminated Open 3 2 1 3 2 1 3 2 1 3 2 1 3 2 1 1 2 3 1 2 3 RS422 INTERFACE SUBASS Y X1 X2 SUBASSEMBLY STRAPPING OPTIONS POSITION STRAP...

Страница 11: ...1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 5 3 5 2 5 2 3 5 1 5 1 3 5 1 2 5 1 2 4 5 5 3 5 2 5 2 3 5 1 5 1 3 5 1 2 5 1 2 4 5 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8 1 2 5 8...

Страница 12: ...RS232 T RS422 O RS422 RS 232 default RS 422 TERMINATED RS 422 NON TERMINATED X1 X2 X3 X4 1 2 3 1 2 3 4 1 2 3 1 2 3 4 1 2 3 4 1 2 3 4 ON OFF POWER SUPPLY S5 1 2 3 4 5 6 7 8 1 2 3 4 5 S1 S6 1 2 3 4 5 6...

Страница 13: ...N 1 ON 1 ON 2 ON 3 ON 3 ON 4 ON 5 ON 5 ON 2 ON 2 ON 1 ON 4 ON 4 ON 3 ON 6 ON 6 ON 6 ON All OFF 5 ON All OFF All OFF All OFF 3 1 2 1 SLOTS 1 10 SLOT 11 POSITION 5 ON 5 ON As needed As needed As needed...

Страница 14: ...4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 O 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6 ON 1 2 3 4 5 6...

Страница 15: ...e the MAP to interrogate the Multi Alarm Transmitters MATs through a large number of LSOs Using the MAP s printer port set the IPD value to 128 500ms The command is IPD 128 This allows enough time for...

Страница 16: ...1 46020 00 MAP Refer to Step 9 and set the straps on the 49029 communication subassembly DATA XMT LED RESET SWITCH 8 7 6 5 4 3 2 1 8 7 6 5 4 3 2 1 S4 S3 S2 8 7 6 5 4 3 2 1 8 7 6 5 4 3 2 1 S7 8 7 6 5 4...

Страница 17: ...cations Set 46010 switches per the following table MAT will be set for address 16 1200 baud normal mode input reversal for points 1 8 Alarm point 3 to operate A level relay alarm point 6 to operate B...

Страница 18: ...tor to C2 of the 46090 in slot 2 shelf D or to C2D of the D shelf Refer to Fig 11 for switch and strap locations Set 46062 strap settings per following table Shelf D Slot 1 A11 46062 22 GPP SETTINGS A...

Страница 19: ...19 FIG 11 GPP SWITCH AND STRAP LOCATIONS GREEN LEDS MASTER PRINTER DATA S3 S2 S1 DOWN ON GPP CARD POWER SUPPLY SUBASSEMBLY BOARD TO BOARD CONNECTOR PINS 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8...

Страница 20: ...Only one switch may be on at a time Refer to the following table A11 46017 01 SWITCH OPTIONS SHELF D SLOT 3 TIME OUT IN 1 minute 4 minutes 8 minutes 16 minutes No time out S1 1 ON OFF OFF OFF OFF S1...

Страница 21: ...allel option not used SWITCH OR STRAP SETTING S1 00 Mode X1 ON X2 ON X3 1 2 FIG 13 49029 SWITCH AND STRAP OPTION LOCATIONS STEP 10 FUSE MODULE CONNECTOR MODULE RELAY MODULES The A11 48001 01 Fuse modu...

Страница 22: ...Fuse Module is installed in slot 14 of shelf A B or C power will be applied to that shelf Inserting the fuse module in shelf C will also place power on shelf D Shelf D fuse protection is con trolled b...

Страница 23: ...rt for the chosen LSO to be tested Use a terminal mode such as the one in the T Shell editor When the user operates the key board one RX LED and two TX LEDs on the appropriate 46034 should turn on The...

Страница 24: ...nections from he fiber terminal to the DSM assembly At the Service Node MAT alarm points 3 6 and 9 will operate as well as relay modules 10A through 13A and 10B through 13B Points 1 or 4 will also tur...

Страница 25: ...of those individual practices Support Documents 1 46112 DSM Controller Module 2 46113 DSM Port Module 3 46034 Hubbing Module 4 44930 00 Relay Module 5 46010 Multiple Alarm Transmitter 6 48001 Fuse Mod...

Страница 26: ...n instrument signed by a duly authorized officer of the Seller and accepted by the Buyer Warranty and remedies on products not manufactured by the Seller are in accordance with warranty of the respect...

Отзывы: