18
|
Piping installation
Installer and user reference guide
99
REMA5+REYA8~20A7Y1B
VRV 5 heat recovery
4P687640-1 – 2022.07
WARNING
NEVER remove the pinched piping by brazing.
Any gas or oil remaining inside the stop valve may blow off the pinched piping.
6
Wait until all oil has dripped out before continuing with the connection of the
field piping in case the recovery was not complete.
18.3 Checking the refrigerant piping
18.3.1 About checking the refrigerant piping
Refrigerant piping works are
finished?
The indoor units / BS units /
outdoor unit are already
powered ON?
Use procedure:
"Method 2: After power ON".
Finish piping work.
Use procedure:
"Method 1: Before power ON
(regular method)".
Yes
No
No
Yes
It is very important that all refrigerant piping work is done before the units
(outdoor, BS unit or indoor) are powered on. When the units are powered on, the
expansion valves will initialise. This means that the valves will close.
NOTICE
Leak test and vacuum drying of field piping, BS units and indoor units is impossible
when field expansion valves are closed.
Method 1: Before power ON
If the system has not yet been powered on, no special action is required to
perform the leak test and the vacuum drying.