Installation manual

5

RZQG71~140L + RZQSG100~Y1B(9)

Split system air conditioners

4P327537-1 – 2012.08

Install a baffle plate on the air suction side of the outdoor unit 
and set the outlet side at a right angle to the direction of the 
wind:

Prepare a water drainage channel around the foundation, to 
drain waste water from around the unit.

If the water drainage of the unit is not easy, please build up the 
unit on a foundation of concrete blocks, etc. (the height of the 
foundation should be maximum 150 mm).

If you install the unit on a frame, please install a waterproof plate 
(field supply) within 150 mm of the underside of the unit in order 
to prevent the invasion of water from the lower direction.

When installing the unit in a place frequently exposed to snow, 
pay special attention to elevate the foundation as high as 
possible.

If you install the unit on a building frame, 
please install a waterproof plate (field 
supply)(within 150 mm of the underside of 
the unit) or use a drain kit in order to avoid 
the drainwater dripping (field supply). (See 
figure).

Make sure that the unit is installed level.

5.2.

Selecting a location in cold climates

To prevent exposure to wind, install the outdoor unit with its 
suction side facing the wall.

Never install the outdoor unit at a site where the suction side 
may be exposed directly to wind.

To prevent exposure to wind, install a baffle plate on the air 
discharge side of the outdoor unit.

In heavy snowfall areas it is very important to select an 
installation site where the snow will not affect the unit and set the 
outlet side at a right angle to the direction of the wind:

6.

Precautions on installation

6.1.

Foundation work

Check the strength and level of the installation ground so that 
the unit will not cause any operating vibration or noise after 
installation.

In accordance with the foundation drawing in the figure, fix the 
unit securely by means of the foundation bolts. (Prepare four 
sets of M12 foundation bolts, nuts and washers each which are 
available on the market.)

It is best to screw in the foundation bolts 
until their length are 20 mm from the 
foundation surface.

Fix the outdoor unit to the foundation bolts using nuts 
with resin washers (1) as shown in the figure. 
If the coating on the fastening area is stripped off, the nuts rust 
easily.
Dimensions (bottom view) (unit of measurement: mm)

A

Front (air outlet side)

B

Leg pitch

C

Bottom frame

D

Drain hole

E

Knock-out hole

NOTICE

When operating the outdoor unit in a low outdoor ambient 
temperature, be sure to follow the instructions described 
below.

1

2

2

3

1

Baffle plate

2

Strong wind

3

Discharge air

NOTICE

If drain holes of the outdoor unit are 
covered by a mounting base or by 
floor surface, raise the unit in order 
to provide a free space of more than 
150 mm under the outdoor unit.

3

3

2

1

4

1

Construct a large 
canopy.

2

Construct a pedestal.

 

Install the unit high 
enough off the ground 
to prevent burying in 
snow.

3

Strong wind

4

Discharge air

•PP

20

1

A

B

B

C

D

E

160

160

620

36

61

262

416

595

285

279

260

161

(345~355)

Содержание SkyAir RZQG71L7V1B

Страница 1: ...RZQG71L7V1B RZQG100L7V1B RZQG125L7V1B RZQG140L7V1B RZQG71L7Y1B9 RZQG100L7Y1B RZQG125L7Y1B RZQG140L7Y1B RZQSG100L7V1B RZQSG125L7V1B RZQSG140L7V1B RZQSG100L7Y1B9 RZQSG125L7Y1B9 RZQSG140L7Y1B Split syst...

Страница 2: ...A B 1 2 4 5 H1 L3 L2 L3 L4 L2 L3 L3 L4 L5 L6 A C E B D H 1 2 3 1 50 Hz 220 240 V 3N 50 Hz 380 415 V V1 type Y1 type 1 2 4 5 A 1 A 2 100 100 100 100 1 1 2 H1 H1 H1 H2 H2 H2 L1 L1 L1 L1 L2 7 R410A R410...

Страница 3: ...com o Certificado C 09 A B C 10 Bem rk som anf rt i A og positivt vurderet af B i henhold til Certifikat C 11 Information enligt A och godk nts av B enligt Certifikatet C 12 Merk som det fremkommer i...

Страница 4: ...run 18 15 4 Precautions regarding test runs 19 15 5 Failure diagnosis at the moment of first installation 19 16 Wiring diagram 20 Thank you for purchasing this product The original instructions are w...

Страница 5: ...at can withstand its weight Insufficient strength may result in the fall of equipment and causing injury Carry out the specified installation work in consideration of strong winds typhoons or earthqua...

Страница 6: ...it is advised to foresee a delay of 10 minutes for signalling the alarm in case the alarm temperature is exceeded The unit may stop for several minutes during normal operation for defrosting the unit...

Страница 7: ...bother next door neighbours Safe places which can withstand the unit s weight and vibration and where the unit can be installed level Places where there is no possibility of flammable gas or product...

Страница 8: ...e outdoor unit In heavy snowfall areas it is very important to select an installation site where the snow will not affect the unit and set the outlet side at a right angle to the direction of the wind...

Страница 9: ...outlet space position the units with consideration to the space required for the onsite refrigerant piping work as well Consult your dealer if the work conditions do not match those in the drawings 7...

Страница 10: ...llation shall comply with applicable legislation In Europe the EN378 is the application standard that shall be used NOTICE To persons in charge of piping work Be sure to open the stop valve after pipi...

Страница 11: ...ze Model 71 100 125 140 Maximum total one way piping length a a Parenthesized figure represents the equivalent length Pair L1 size down 10 m 10 m standard 50 m 70 m 75 m 90 m size up 25 m 35 m 35 m 45...

Страница 12: ...ecause using existing piping with deteriorated oil will cause compressor breakdown Put some residual oil of the pipes you want to reuse on a piece of white paper or on the white surface of an oil chec...

Страница 13: ...ine it will deteriorate the refrigerant oil 9 3 Stop valve operation Cautions on handling the stop valve Make sure to keep both stop valves open during operation The figure below shows the name of eac...

Страница 14: ...to the edge and the surrounding end surfaces to prevent rusting When passing electrical wiring through the knock out holes remove any burrs from the knock out holes and wrap the wiring with protective...

Страница 15: ...leaks Use a 2 stage vacuum pump with a non return valve which can evacuate to a gauge pressure of 100 7 kPa 5 Torr absolute 755 mm Hg Connect the vacuum pump to both the service port of the gas stop...

Страница 16: ...the leak test and vacuum drying see 11 Leak test and vacuum drying on page 12 This unit requires additional charging of refrigerant according to the length of refrigerant piping connected at the site...

Страница 17: ...kg b G2 12 m 6 4 R2 0 6 kg 3 Refrigerant charge amount R R1 R2 0 5 0 6 1 1 kg Example 2 1 G1 L1 5 m G2 L2 L3 L4 17 17 20 54 2 Over 30 m a G1 5 m R1 0 0kg b G1 G2 30 5 54 30 29 6 4 R2 0 9 kg 3 Refrige...

Страница 18: ...nding on mode type RZQG71 RZQSG100 125 RZQG100 140 RZQSG140 Model Liquid piping Refrigerant piping length 5 10 m a b a For RZQG units only 3 10 m b For RZQG units only When piping length is less than...

Страница 19: ...t wiring Secure the earth wire to the stop valve attachment plate so that it does not slide Secure the earth wire to the stop valve attachment plate one more time along with the electric wiring and th...

Страница 20: ...esponsibility of the installer or user of the equipment to ensure by consultation with the distribution network operator if necessary that the equipment is connected only to a supply with a short circ...

Страница 21: ...the wiring as mentioned on the wiring diagram Make sure no wiring has been forgotten and that there are no missing phases or reverse phases Is the unit properly grounded Is the wiring between units co...

Страница 22: ...tector of this product only works during the initialisation stage after a power reset The reversed phase protection detector is designed to stop the product in case of an abnormality when the product...

Страница 23: ...or heat exchanger middle R6T Thermistor liquid R10T Thermistor fin RC V1B Signal receiver circuit S1PH High pressure switch TC V1B Signal transmission circuit V1R IGBT power module V1T V1B Insulated g...

Страница 24: ...4P327537 1 2012 08 Copyright 2012 Daikin...

Отзывы: