Daikin SkyAir FCAHG71GVEB Скачать руководство пользователя страница 20

8 Commissioning

Installer and user reference guide

20

FCAHG71~140GVEB

Split system air conditioners

4P482875-1 – 2017.03

8

Commissioning

8.1

Overview: Commissioning

This  chapter  describes  what  you  have  to  do  and  know  to
commission the system after it is installed.

Typical workflow

Commissioning typically consists of the following stages:

1

Checking the "Checklist before commissioning".

2

Performing a test run for the system.

8.2

Precautions when commissioning

INFORMATION

During  the  first  running  period  of  the  unit,  the  required
power may be higher than stated on the nameplate of the
unit.  This  phenomenon  is  caused  by  the  compressor,  that
needs  a  continuous  run  time  of  50  hours  before  reaching
smooth operation and stable power consumption.

NOTICE

Before starting up the system, the unit MUST be energised
for at least 6 hours to avoid compressor breakdown during
startup.

NOTICE

NEVER  operate  the  unit  without  thermistors  and/or
pressure  sensors/switches.  Burning  of  the  compressor
might result.

NOTICE

Do  NOT  operate  the  unit  until  the  refrigerant  piping  is
complete  (when  operated  this  way,  the  compressor  will
break).

NOTICE

Cooling  operation  mode

.  Perform  the  test  run  in  cooling

operation mode so that stop valves failing to open can be
detected.  Even  if  the  user  interface  was  set  to  heating
operation mode, the unit will run in cooling operation mode
during 2‑3 minutes (although the user interface will display
the heating icon), and then automatically switch to heating
operation mode.

NOTICE

If  you  cannot  operate  the  unit  in  test  run,  see 

"8.5  Error

codes when performing a test run" on page 21

.

WARNING

If the panels on the indoor units are not installed yet, make
sure  to  power  OFF  the  system  after  finishing  the  test  run.
To  do  so,  turn  OFF  operation  via  the  user  interface.  Do
NOT stop operation by turning OFF the circuit breakers.

8.3

Checklist before commissioning

Do NOT operate the system before the following checks are OK:

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

In case a wireless user interface is used: The 

indoor unit

decoration panel

 with infrared receiver is installed.

The 

outdoor unit

 is properly mounted.

There are NO 

missing phases

 or 

reversed phases

.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed  according  to  this  document,  and  have  not  been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

8.4

To perform a test run

This  task  is  only  applicable  when  using  the  BRC1E52  or  BRC1E53
user  interface.  When  using  any  other  user  interface,  see  the
installation manual or service manual of the user interface.

NOTICE

Do not interrupt the test run.

INFORMATION

Backlight.

  To  perform  an  ON/OFF  action  on  the  user

interface,  the  backlight  does  not  need  to  be  lit.  For  any
other  action,  it  needs  to  be  lit  first.  The  backlight  is  lit  for
±30 seconds when you press a button.

1

Perform introductory steps.

#

Action

1

Open the liquid stop valve (A) and gas stop valve (B)
by removing the stem cap and turning
counterclockwise with a hex wrench until it stops.

A

B

2

Close the service cover to prevent electric shocks.

3

Turn ON power for at least 6 hours before starting
operation to protect the compressor.

4

On the user interface, set the unit to cooling operation
mode.

2

Start the test run

#

Action

Result

1

Go to the home menu.

Cool

Set to

28

°C

Содержание SkyAir FCAHG71GVEB

Страница 1: ...Installer and user reference guide Split system air conditioners English Installer and user reference guide Split system air conditioners FCAHG71GVEB FCAHG100GVEB FCAHG125GVEB FCAHG140GVEB...

Страница 2: ...ca acestea s fie utilizate n conformitate cu instruc iunile noastre skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z na imi navodili on vastavuses j rgmis...

Страница 3: ...wiring components 17 6 4 5 To connect the electrical wiring on the indoor unit 17 7 Configuration 18 7 1 Field settings 18 8 Commissioning 20 8 1 Overview Commissioning 20 8 2 Precautions when commis...

Страница 4: ...ildren aged from 8 years and above and persons with reduced physical sensory or mental capabilities or lack of experience and knowledge if they have been given supervision or instruction concerning us...

Страница 5: ...s weight and vibration Make sure the area is well ventilated Do NOT block any ventilation openings Make sure the unit is level Do NOT install the unit in the following places In potentially explosive...

Страница 6: ...7 3 6 4 351 3 0 5 74 6 6 27 8 3 0 77 2 6 6 374 3 2 6 54 6 8 29 5 3 2 87 9 6 8 397 3 4 7 38 7 0 31 3 3 4 99 2 7 0 420 3 6 8 27 7 2 33 1 3 6 111 7 2 445 3 8 9 22 7 4 34 9 3 8 124 7 4 470 4 0 10 2 7 6 36...

Страница 7: ...wn Open refrigerant cylinders slowly Charge the refrigerant in liquid form Adding it in gas form may prevent normal operation CAUTION When the refrigerant charging procedure is done or when pausing cl...

Страница 8: ...e all covers are closed before starting up the unit NOTICE Only applicable if the power supply is three phase and the compressor has an ON OFF starting method If there exists the possibility of revers...

Страница 9: ...e Large gas pipe 4 About the units and options 4 1 Overview About the units and options This chapter contains information about Combining outdoor and indoor units Combining the indoor unit with option...

Страница 10: ...ral installation site requirements See the General safety precautions chapter Refrigerant piping requirements length height difference See further in this Preparation chapter INFORMATION The sound pre...

Страница 11: ...orners open optional blocking pad kit required c Air outlet and corners closed optional blocking pad kit required B Minimum and maximum distance to the floor Minimum 2 5 m to avoid accidental touching...

Страница 12: ...ion This chapter describes what you have to do and know on site to install the system Typical workflow Installation typically consists of the following stages Mounting the outdoor unit Mounting the in...

Страница 13: ...een the unit and the ceiling opening C Overlap between the decoration panel and the suspended ceiling Installation guide Use the installation guide to determine the correct vertical position A B C a b...

Страница 14: ...tion 2 Tighten the metal clamp until the screw head is less than 4 mm from the metal clamp part 3 Check for water leaks see To check for water leaks on page 14 4 Install the insulation piece drain pip...

Страница 15: ...to account Avoid anything but the designated refrigerant to get mixed into the refrigerant cycle e g air Only use R32 or R410A1 when adding refrigerant Only use installation tools e g manifold gauge s...

Страница 16: ...and compressors in the refrigerating system and prevents proper operation Set the nitrogen pressure to 20 kPa 0 2 bar just enough so it can be felt on the skin with a pressure reducing valve a b c d e...

Страница 17: ...Terminal b Screw c Flat washer Tightening torques Wiring Screw size Tightening torque N m Interconnection cable indoor outdoor M4 1 18 1 44 User interface cable M3 5 0 79 0 97 6 4 4 Specifications of...

Страница 18: ...ollers control 1 indoor unit 1 50 Hz 220 240 V b a e2 e1 c d a Interconnection cable b Power supply cable c Earth leakage circuit breaker d Fuse e1 Main user interface e2 Optional user interface Force...

Страница 19: ...en4 M C1 C2 2500 h light 10 20 0 01 1250 h heavy 02 No notification 3 02 Individual setting in a simultaneous operation system We recommend using the optional user interface to set the slave unit Perf...

Страница 20: ...kers 8 3 Checklist before commissioning Do NOT operate the system before the following checks are OK You read the complete installation instructions as described in the installer reference guide The i...

Страница 21: ...er supply and outdoor unit between outdoor unit and indoor units between indoor unit and user interface The fuse on the outdoor or indoor unit PCB has blown E3 E4 or L8 The stop valves are closed The...

Страница 22: ...l data Installer and user reference guide 22 FCAHG71 140GVEB Split system air conditioners 4P482875 1 2017 03 11 1 Piping diagram Indoor unit b a c a Liquid pipe connection b Gas pipe connection c Hea...

Страница 23: ...L OVERLOADPROTECTOR D V D DIODE Q M THERMOSWITCH DB DIODEBRIDGE R RESISTOR DS DIPSWITCH R T THERMISTOR E H HEATER RC RECEIVER F U FU FORCHARACTERISTICS REFERTOPCBINSIDEYOURUNIT FUSE S C LIMITSWITCH F...

Страница 24: ...ech Republic A B C D E FCAHG125 7 83 4 27 13 50 0 25 61 FCAHG140 8 68 4 72 15 50 0 25 61 13 User interface CAUTION Never touch the internal parts of the controller Do not remove the front panel Some p...

Страница 25: ...erant cycle will reverse and energy from inside the building will be used to defrost the outdoor unit coil The indoor unit will indicate defrost operation on the display Hot start In order to prevent...

Страница 26: ...keep the temperature setting at a moderate level Never place objects near the air inlet or the air outlet of the unit It may cause deterioration in the effect or stop the operation Turn off the main...

Страница 27: ...loration and deformation 1 Open the suction grille 1 2 Remove the suction grille 45 1 2 3 Remove the air filter 1 2 3 4 Clean the suction grille Wash with a soft bristle brush and water or neutral det...

Страница 28: ...es service and warranty 17 5 1 Warranty period This product includes a warranty card that was filled in by the dealer at the time of installation The completed card has to be checked by the customer a...

Страница 29: ...to taking apart or cleaning interiors of units by anyone other than our authorised dealers may not be included in the warranty 18 Troubleshooting If one of the following malfunctions occur take the me...

Страница 30: ...eration Moisture generated by defrost becomes steam and is exhausted 18 1 6 Symptom The user interface display reads U4 or U5 and stops but then restarts after a few minutes This is because the user i...

Страница 31: ...can perform or coordinate the required service to the product Installation manual Instruction manual specified for a certain product or application explaining how to install configure and maintain it...

Страница 32: ...4P482875 1 2017 03 Copyright 2017 Daikin...

Отзывы: