Route the wiring harness through the harness retainer (top of the switch box).
3
Connect the other end of the front panel motor wiring harness to the indoor
unit main PCB.
Is the problem solved?
Action
Yes
No further actions required.
No
Return to the troubleshooting of the
specific error and continue with the
next procedure.
4.6 High pressure switch
4.6.1 Checking procedures
To perform an electrical check of the high pressure switch
Prerequisite:
Stop the unit operation via the user interface.
Prerequisite:
Turn OFF the respective circuit breaker.
Prerequisite:
Remove the required plate work, see
1
Recuperate the refrigerant from the refrigerant circuit, see
216].
2
Fill the refrigerant circuit with nitrogen until pressurized just below operating
pressure of the high pressure switch.
a
b
e
f
d
c
a
High pressure switch protection control
b
Pressure
c
High pressure switch closed
d
High pressure switch open
e
High pressure switch operating pressure
f
High pressure switch reset pressure
High pressure switch
Operating pressure (MPa) Reset pressure (MPa)
S1PH
4.03~4.15
3.05~3.35
3
Disconnect the Faston connectors from the high pressure switch.
INFORMATION
Measure the continuity of all wiring between the high pressure switch and the
appropriate PCB. If NO continuity is measured, repair as needed, see
4
Measure the resistance between the Faston connections of the high pressure
switch.
Result:
The switch MUST be closed.