Installation
Si39-406
32
General Information
Heat Recovery
Series
Suction, Discharge Gas piping, liquid piping must be insulated.
Example of thermal insulation work.
If you think the humidity around the cooling piping might exceed 86°F and RH80%, reinforce the
insulation on the cooling piping (at least 13/16" thick). Condensation might from on the surface
of the insulation.
3.2.5
Air Tight Test
Operational steps
Essential Points
of Testing
(Maintaining
Pressure Over a
Period)
The key to successful testing is strict adherence to the following procedure:
a) The liquid and gas piping in each refrigerant system should be pressurized in turn in accordance
with the following steps. (Nitrogen gas must be used.)
∗
Increasing the system pressure to 551psi does not guarantee the identification of minor leaks if
pressure is maintained for only a short time. It is therefore recommended that the system remain
pressurized in accordance with Step 3 above for at least 24 hours.
Note:
The pressure must on no account be increased beyond 551psi.
b) Check for pressure drop
If there is no drop in pressure then the test is deemed a success.
If the pressure drops then the leak must be located. See following page.
However, if there is a change in the ambient temperature between the pressurizing stage and
the time when you check for a drop in pressure then you will have to adjust your calculations
accordingly since a change of 1°F can account for a pressure change of approximately 0.80psi.
Compensating adjustment value:
(temperature at time of pressurizing – temperature at time of checking) × 0.80
Example:
Time of pressurizing: 551psi 77°F
3 piping section (between outdoor unit and BS unit)
2 piping section (between BS unit and indoor unit)
Complete
refrigerant pipe
installation work
Pressurize
Check for pressure drop
Success
Locate and repair leaks
(V0987)
Step 1: increase pressure to 13.05psi for 3
minutes or more
Indicates existence of major leaks
Step 2: increase pressure to 217psi for 5
minutes or more
Indicates existence of minor leaks
Step 3: increase pressure to 551psi for
approx. 24 hours
Содержание REYQ96MTJU
Страница 1: ...Design Installation Testing Instruction R410A Heat Recovery 60Hz REYQ96MTJU Si39 406...
Страница 6: ...Si39 406 iv Table of Contents...
Страница 34: ...Installation Si39 406 28 General Information Flaring Procedure...
Страница 68: ...Installation Si39 406 62 General Information Caution Caution label 3P124617 4P124614...
Страница 114: ...Appendix Si39 406 108 General Information 3P135887 1...
Страница 124: ...Appendix Si39 406 118 General Information 7 8 Piping System Diagrams 7 8 1 Outdoor Unit REYQ96MTJU 4D045329...
Страница 126: ...Appendix Si39 406 120 General Information 7 8 3 BS Unit BSVQ36MVJ BSVQ60MVJ 4D045338...
Страница 127: ...Si39 406 Appendix General Information 121 7 9 Wiring Diagrams 7 9 1 Outdoor Unit REYQ96MTJU 3D044892A...
Страница 128: ...Appendix Si39 406 122 General Information 7 9 2 Field Wiring REYQ96MTJU 3D042647A...
Страница 156: ...Refrigerant Piping Si39 406 150 Installation Manual REYQ96MTJU...
Страница 158: ...Refrigerant Piping Si39 406 152 Installation Manual REYQ96MTJU...
Страница 230: ...Precautions for New Refrigerant R410A Si39 406 224 Precautions for New Refrigerant R410...
Страница 236: ...375 Park Avenue Suite 3308 New York N Y 10152 info daikinac com www daikinac com...