8 Commissioning
Installer reference guide
19
FTXA25~50(A)(B)2V1B(W)(S)(T)(B)
Daikin room air conditioner
4P518023-3F – 2019.10
8
Commissioning
8.1
Overview: Commissioning
This chapter describes what you have to do and know to
commission the system after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
8.2
Checklist before commissioning
After the installation of the unit, first check the items listed below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.
You read the complete installation instructions, as
described in the
installer reference guide
.
The
indoor units
are properly mounted.
The
outdoor unit
is properly mounted.
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT
obstructed by paper sheets, cardboard, or any other
material.
There are NO
missing phases
or
reversed phases
.
The
refrigerant pipes
(gas and liquid) are thermally
insulated.
Drainage
Make sure drainage flows smoothly.
Possible consequence:
Condensate water might drip.
The system is properly
earthed
and the earth terminals
are tightened.
The
fuses
or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The
power supply voltage
matches the voltage on the
identification label of the unit.
The specified wires are used for the
interconnection
cable
.
The indoor unit receives the signals of the
user interface
.
There are NO
loose connections
or damaged electrical
components in the switch box.
The
insulation resistance
of the compressor is OK.
There are NO
damaged components
or
squeezed
pipes
on the inside of the indoor and outdoor units.
There are NO
refrigerant leaks
.
The correct pipe size is installed and the
pipes
are
properly insulated.
The
stop valves
(gas and liquid) on the outdoor unit are
fully open.
8.3
To perform a test run
Prerequisite:
Power supply MUST be in the specified range.
Prerequisite:
Test run may be performed in cooling or heating
mode.
Prerequisite:
Test run should be performed in accordance with the
operation manual of the indoor unit to make sure that all functions
and parts are working properly.
1
In cooling mode, select the lowest programmable temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.
2
When the test run is finished, set the temperature to a normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.
3
The system stops operating 3 minutes after the unit is turned
OFF.
8.3.1
To perform a test run using the user
interface
1
Press
to switch the system on.
2
Press
and
simultaneously.
3
Press
, select
and press
.
Result:
Test run operation will stop automatically after about
30 minutes.
4
To stop operation sooner, press
.
9
Hand-over to the user
Once the test run is finished and the unit operates properly, please
make sure the following is clear for the user:
▪ Make sure that the user has the printed documentation and ask
him/her to keep it for future reference. Inform the user that he can
find the complete documentation at the URL mentioned earlier in
this manual.
▪ Explain the user how to properly operate the system and what to
do in case of problems.
▪ Show the user what to do for the maintenance of the unit.
10
Disposal
NOTICE
Do NOT try to dismantle the system yourself: dismantling
of the system, treatment of the refrigerant, oil and other
parts MUST comply with applicable legislation. Units
MUST be treated at a specialised treatment facility for
reuse, recycling and recovery.
11
Technical data
▪ A
subset
of the latest technical data is available on the regional
Daikin website (publicly accessible).
▪ The
full set
of latest technical data is available on the Daikin
Business Portal (authentication required).
11.1
Wiring diagram
The wiring diagram is delivered with the unit, located inside of
the outdoor unit (bottom side of the top plate).
11.1.1
Unified wiring diagram legend
For applied parts and numbering, refer to the wiring diagram on the
unit. Part numbering is by Arabic numbers in ascending order for
each part and is represented in the overview below by "*" in the part
code.