Pre-Test Run Checks
ESIE11-02
4–4
Part 4 – Commissioning and Test Run
3
1
4
5
1.2
General Checks
Checklist
The table below contains the general checklist.
Step
Check whether...
1
There is external damage.
2
The unit is properly supported and/or has a proper foundation.
3
The unit is installed horizontally with a deviation of maximum 1°.
4
Anti-vibration pads are required.
5
Is the chiller of the type EUWY*5-24KBZW1?
■
When yes, go to step 6.
■
When no, go to step 8.
6
There is a drain possibility for condensed water.
7
A heater tape is placed inside the drain system. This is necessary to prevent ice accumu-
lation and possible blockage during wintertime.
8
Check for remaining metal dust of burrs. Metal dust or burrs from grinding or drilling in the
metal parts during construction facilitates the rust process and shortens the lifetime of the
unit.
9
The operator has received the operation manual.
10
The installer has received the installation manual.
11
The air volume over the coil is adequate; there is no blockage (from paper, plastic...) or air
short circuit due to wrong positioning.
Содержание EUWAB10KBZW1
Страница 2: ......
Страница 8: ...ESIE11 02 vi Table of Contents 3 1 4 5...
Страница 10: ...Introduction ESIE11 02 viii 3 1 4 5...
Страница 12: ...ESIE11 02 1 2 Part 1 System Outline 3 1 1 5...
Страница 86: ...Wiring Layout ESIE11 02 1 76 Part 1 System Outline...
Страница 88: ...ESIE11 02 2 2 Part 2 Functional Description 3 1 2 5...
Страница 128: ...The Digital Controller ESIE11 02 2 42 Part 2 Functional Description 3 1 2 4 5...
Страница 130: ...ESIE11 02 3 2 Part 3 Troubleshooting 3 1 3 5...
Страница 168: ...ESIE11 02 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Страница 198: ...Test Run and Operation Data ESIE11 02 4 32 Part 4 Commissioning and Test Run 3 1 4 5...
Страница 200: ...ESIE11 02 5 2 Part 5 Maintenance 3 1 5...
Страница 210: ...ESIE11 02 4 Index 3 1 4 5...