7.2.6 To close the indoor unit
1
Reconnect the ground connection to the top cover of the switch box.
2
Close the cover of the switch box.
3
Reinstall the top cover.
4
Check that the top cover is correctly fitted.
5
Screw in the top cover screws to secure it.
6
Put the switch box back into place.
7
Reinstall the user interface panel.
NOTICE
When closing the indoor unit, make sure that the tightening torque does NOT exceed
4.1 N•m.
7.3 Mounting the outdoor unit
7.3.1 About mounting the outdoor unit
When
You have to mount the outdoor and indoor unit before you can connect the
refrigerant and water piping.
Typical workflow
Mounting the outdoor unit typically consists of the following stages:
1
Providing the installation structure.
2
Installing the outdoor unit.
3
Preventing the unit from falling over.
4
Protecting the unit against snow and wind by installing a snow cover and baffle
plates. See
"7.1 Preparing the installation site"
65].
7.3.2 Precautions when mounting the outdoor unit
INFORMATION
Also read the precautions and requirements in the following chapters:
▪
"2 General safety precautions"
▪
"7.1 Preparing the installation site"
7.3.3 To provide the installation structure
Check the strength and level of the installation ground so that the unit will not
cause any operating vibration or noise.
Fix the unit securely by means of foundation bolts in accordance with the
foundation drawing.
This topic shows different installation structures. For all, use 4 sets of M8 or M10
anchor bolts, nuts and washers. In any case, provide at least 300 mm of free space
below the unit. Additionally, make sure the unit is positioned at least 100 mm
above the maximum expected level of snow.