12
|
Commissioning
Installer reference guide
249
ERGA04~V3A+V37 + EHSH/X(B)04+08P30+50EF
Daikin Altherma 3 R ECH₂O
4P678716-1A – 2022.07
▪
Backup heater 2
test
▪
Pump
test
INFORMATION
Make sure that all air is purged before executing the test run. Also avoid disturbances
in the water circuit during the test run.
▪
Shut off valve
test
▪
DHW signal
test
▪
Bivalent signal
test
▪
Alarm output
test
▪
C/H signal
test
▪
DHW pump
test
▪
Tank valve
test
▪
Bypass valve
test
▪
Bizone kit direct pump
test (bizone kit EKMIKPOA or EKMIKPHA)
▪
Bizone kit mixed pump
test (bizone kit EKMIKPOA or EKMIKPHA)
▪
Bizone kit mixing valve
test (bizone kit EKMIKPOA or EKMIKPHA)
12.4.5 Underfloor heating screed dryout
About underfloor heating screed dryout
Purpose
The underfloor heating (UFH) screed dryout function is used for drying out the
screed of an underfloor heating system during the construction of the building.
NOTICE
The installer is responsible for:
▪
contacting the screed manufacturer for the maximum allowed water
temperature, to avoid cracking the screed,
▪
programming the underfloor heating screed dryout schedule according to the
initial heating instructions of the screed manufacturer,
▪
checking the proper functioning of the setup on a regular basis,
▪
performing the correct program complying with the type of the used screed.
UFH screed dryout before or during installation of outdoor unit
The UFH screed dryout function can be executed without finishing the outdoor
installation. In this case, the backup heater will perform the screed dryout and
supply the leaving water without heat pump operation.
UFH screed dryout after installation of outdoor unit
If the outdoor ambient temperature and [4‑02] setting > 25°C the backup heater
will perform the screed dryout and supply the leaving water without heat pump
operation.
To program an underfloor heating screed dryout schedule
Duration and temperature
The installer can program up to 20 steps. For each step he needs to enter: