4 Unit installation
Installation manual
8
ARXF20~42E5V1B
R32 split series
3P650253-12T – 2023.04
In heavy snowfall areas it is very important to select an installation
site where the snow will NOT affect the unit. If lateral snowfall is
possible, make sure that the heat exchanger coil is NOT affected by
the snow. If necessary, install a snow cover or shed and a pedestal.
4.2
Mounting the outdoor unit
4.2.1
To provide the installation structure
Prepare 4 sets of M8 or M10 anchor bolts, nuts and washers (field
supply).
20 mm
300
470
192
(mm)
192
a
a
100 mm above expected level of snow
4.2.2
To install the outdoor unit
4× M8/M10
4.2.3
To provide drainage
NOTICE
If the unit is installed in a cold climate, take adequate
measures so that the evacuated condensate CANNOT
freeze.
NOTICE
If the drain holes of the outdoor unit are blocked up by a
mounting base or floor surface, place additional foot bases
≤30 mm under the outdoor unit's feet.
INFORMATION
For information on the available options, contact your
dealer.
1
Use a drain plug for drainage.
2
Use a Ø16 mm hose (field supply).
a
c
b
d
a
Drain port
b
Bottom frame
c
Drain plug
d
Hose (field supply)
4.2.4
To prevent the outdoor unit from falling
over
In case the unit is installed in places where strong wind can tilt the
unit, take following measure:
1
Prepare 2 cables as indicated in the following illustration (field
supply).
2
Place the 2 cables over the outdoor unit.
3
Insert a rubber sheet between the cables and the outdoor unit
to prevent the cables from scratching the paint (field supply).
4
Attach the ends of the cables.
5
Tighten the cables.