7 Installation
Installer reference guide
41
ERGA04~08DAV3(A) + 08S23DAV
Daikin Altherma – Low temperature split
4P499573-1A – 2018.11
NOTICE
▪ A drain device and pressure relief device must be
installed on the cold water inlet connection of the
domestic hot water cylinder.
▪ To avoid back siphonage, it is recommended to install a
non-return valve on the water inlet of the domestic hot
water tank in accordance with the applicable legislation.
▪ It is recommended to install the pressure relief valve on
a higher position than the top of the domestic hot water
tank. Heating of the domestic hot water tank causes
water to expand and without pressure relief valve the
water pressure inside the tank can rise above the tank
design pressure. Also the field installation (piping,
tapping points, etc.) connected to the tank is subjected
to this high pressure. To prevent this, a pressure relief
valve needs to be installed. The overpressure
prevention depends on the correct operation of the field
installed pressure relief valve. If this is NOT working
correctly, overpressure will deform the tank and water
leakage may occur. To confirm good operation, regular
maintenance is required.
7.8.4
To connect the recirculation piping
Prerequisite:
Only required if you need recirculation in your system.
1
Remove the top panel from the unit, see
2
Cut out the rubber grommet on top of the unit, and remove the
stop. The recirculation connector is placed below the hole.
3
Route the recirculation piping through the grommet and connect
it to the recirculation connector.
4
Reattach the top panel.
7.8.5
To fill the water circuit
To fill the water circuit, use a field supply filling kit. Make sure you
comply with the applicable legislation.
INFORMATION
Make sure both air purge valves (one on the magnetic
filter, and one between the 3‑way valve and flow sensor)
are open.
7.8.6
To fill the domestic hot water tank
1
Open every hot water tap in turn to purge air from the system
pipe work.
2
Open the cold water supply valve.
3
Close all water taps after all air is purged.
4
Check for water leaks.
5
Manually operate the field-installed pressure relief valve to
ensure a free water flow through the discharge pipe.
NOTICE
To operate the system, the domestic hot water tank needs
to be filled completely. Turning on the system when the
tank is not full can damage the integrated anti-legionella
heater and cause electrical errors.
7.8.7
To insulate the water piping
The piping in the complete water circuit MUST be insulated to
prevent condensation during defrost operation and reduction of the
heating capacity.
If the temperature is higher than 30°C and the humidity is higher
than RH 80%, the thickness of the insulation materials should be at
least 20 mm to prevent condensation on the surface of the
insulation.
7.9
Connecting the electrical wiring
7.9.1
About connecting the electrical wiring
Before connecting the electrical wiring
Make sure:
▪ The refrigerant piping is connected and checked
▪ The water piping is connected
Typical workflow
Connecting the electrical wiring typically consists of the following
stages:
1
Making sure the power supply system complies with the
electrical specifications of the heat pump.
2
Connecting the electrical wiring to the outdoor unit.
3
Connecting the electrical wiring to the indoor unit.
4
Connecting the main power supply.
5
Connecting the shut-off valves.
6
Connecting the electrical meters.
7
Connecting the domestic hot water pump.
8
Connecting the alarm output.
9
Connecting the space heating ON/OFF output.
10
Connecting the changeover to an external heat source.
11
Connecting the power consumption digital inputs.
12
Connecting the safety thermostat.
13
Connecting the anti-legionella heater power supply.
7.9.2
About electrical compliance
Only for ERGA04~08DAV3 (not for ERGA04~08DAV3A)
Equipment complying with EN/IEC 61000‑3‑12 (European/
International Technical Standard setting the limits for harmonic
currents produced by equipment connected to public low-voltage
systems with input current >16 A and ≤75 A per phase.).
7.9.3
Precautions when connecting the
electrical wiring
INFORMATION
Also read the precautions and requirements in the
following chapters:
▪ General safety precautions
▪ Preparation
DANGER: RISK OF ELECTROCUTION
WARNING
ALWAYS use multicore cable for power supply cables.