12
|
Commissioning
Installer reference guide
250
ERLA11~W1 + EBSH/X(B)11+16P30+50DF
Daikin Altherma 3 R ECH₂O
4P663482-1A – 2021.11
The
refrigerant pipes
(gas and liquid) are thermally insulated.
The correct pipe size is installed and the
pipes
are properly insulated.
There is NO
water leak
inside the indoor unit. All electric components and connections are
dry.
The
shut-off valves
are properly installed and fully open.
The
automatic air purge
valves are open.
The
pressure relief valve
purges water when opened. Clean water MUST come out.
The
minimum water volume
is guaranteed in all conditions. See "To check the water
The
storage tank
is filled completely.
12.4 Checklist during commissioning
The
minimum flow rate
during backup heater/defrost operation is guaranteed in all
conditions. See "To check the water volume and flow rate" in
To perform an
air purge
.
To perform a
test run
.
To perform an
actuator test run
.
Underfloor screed dryout function
The underfloor screed dryout function is started (if necessary).
12.4.1 Minimum flow rate
Purpose
For a correct operating unit, it is important to check if the minimum flow rate is
reached. If needed, modify the bypass valve setting.
If operation is…
Then the minimum required flow rate
is…
Cooling
16 l/min
Heating/defrost
22 l/min
To check the minimum flow rate
1
Check the hydraulic configuration to find out which space
heating loops can be closed by mechanical, electronic, or other
valves.
—
2
Close all space heating loops that can be closed.
—
3
—
4
Read out the flow rate
(a)
and modify the bypass valve setting to
reach the minimum required flow rate + 2 l/min.
—
(a)
During pump test run, the unit can operate below the minimum required flow rate.