11
|
Commissioning
Installer reference guide
162
EPGA11~16DAV3(7) + EA23DA6V(7)+9W
Daikin Altherma 3 H F
4P556075-1A – 2021.09
NOTICE
To perform an underfloor heating screed dryout, room frost protection needs to be
disabled ([2‑06]=0). By default, it is enabled ([2‑06]=1). However, due to the
"installer-on-site" mode (see "Commissioning"), room frost protection will be
automatically disabled for 12 hours after the first power-on.
If the screed dryout still needs to be performed after the first 12 hours of power-on,
manually disable room frost protection by setting [2‑06] to "0", and KEEP it disabled
until the screed dryout has finished. Ignoring this notice will result in cracking of the
screed.
NOTICE
For the underfloor heating screed dryout to be able to start, make sure the following
settings are met:
▪
[4‑00]=1
▪
[C‑02]=0
▪
[D‑01]=0
▪
[4‑08]=0
▪
[4‑01]≠1
The installer can program up to 20 steps. For each step he needs to enter:
1
the duration in hours, up to 72 hours,
2
the desired leaving water temperature, up to 55°C.
Example:
t
T
A1
25°C (1)
35°C (2)
24h (1)
36h (2)
T
Desired leaving water temperature (15~55°C)
t
Duration (1~72 h)
(1)
Action step 1
(2)
Action step 2
To program an underfloor heating screed dryout schedule
1
Set the user permission level to
Installer
88].
—
2
Go to [A.4.2]:
Commissioning
>
UFH screed dryout
>
Program
.
3
Program the schedule:
To add a new step, select an empty line and change its value.
To delete a step and all steps below it, decrease the duration to
"–".
—
▪
Scroll through the schedule.
▪
Adjust the duration (between 1 and 72 hours) and
temperatures (between 15°C and 55°C).
4
Press the left dial to save the schedule.