Installation Procedures
14
Caution:
Before you apply power to the I/SITE LAN, ensure that the 24 VAC secondary leads are
connected only to TB1. Connection to any other terminal block will damage the I/SITE
LAN. The transformer secondary leads (24 VAC) should
not
be connected to ground.
1.
Connect the 24 VAC input leads from a separate, isolated 24 VAC/40VA trans-
former, to terminals 1 and 2 of terminal block TB1.
2.
Connect terminal 3 of TB1 to a good earth ground using 14 AWG wire (2.081 mm
2
wire).
Grounding Requirements
Earth Ground
To ensure proper operation of the controller, it is imperative that the unit be correctly
grounded. The controller chassis will not provide ground for the input power circuit and
interconnected sensors/devices. Terminal block TB3 must be connected to an Earth
ground.
LAN Ground
Note:
This procedure applies to all LAN and subLAN connections.
✦
Ensure that the subLAN cable shield drain wire is
not
connected to the controller
subLAN terminal block.
✦
Shield drain wire continuity must be maintained as the subLAN cable passes
through each controller. Shield drain wires from each controller subLAN cable
must be spliced together, insulated, and tied back such that wires do not come in
contact with ground or any conductive surface within a controller.
✦
Connect the shield drain wire directly to Electrical Service Earth Ground at
only
one end of the cable (e.g., typically at the I/SITE LAN).
Figure 9. I/SITE LAN Power Connection
24VAC
GND
1 2 3
1 2 3
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5
TB1
TB2
TB3
P5
P3
12
1
24 VAC
Transformer
24VAC
P4
TB4
Earth
Ground