Description

The Crestron

®

 FT2A-UTK-PWS is a 24 Vdc power supply that is used to supply power to 

the power bus in an FT2-ELEC assembly. The FT2A-UTK-PWS can replace the power 
supply that ships with the FT2-ELEC, or it can be used to supply additional power to the 
FT2-ELEC if two FT2A-CHGR-USBA/C modules are installed as part of the 
FlipTop™ system.

Additional Resources

Visit the product page on the Crestron website (

www.crestron.com

for additional information and the latest firmware updates. Use a QR 
reader application on your mobile device to scan the QR image.

Installation

Use the following procedure to install the FT2A-UTK-PWS.

NOTE:

  Connect the power supply to the power bus prior to installing any modules.

NOTE:

  Two power supplies are required if installing two FT2A-CHGR-USBA/C modules 

in the FT2-ELEC. For more information, refer to the FT2A-CHGR-USBA/C Installation 
Guide (Doc. 8219) at 

www.crestron.com/manuals

.

  1.  Underneath the table, connect the power supply to the bottom of the power bus as 

follows:

 

a.  If connecting one power supply to the power bus, connect the dual connector 

ends of the included Y-adapter cable to the two barrel jacks under the power bus. 
Then, connect the power supply’s power cord to the single connector end of the 
Y-adapter.

 

  Y-Adapter Cable

Power supply

holder

FT2A-UTK-PWS

FT2-ELEC assembly

 

FT2A-UTK-PWS Mounting Locations

FT2A-UTK-PWS

mounting 

locations (6)

NOTE:

  Ensure that the unit is properly grounded by connecting the chassis 

ground lug to an earth ground (building steel).

  2.  Dress the power cord and secure it to the cable management bar on the bottom of 

the assembly. Refer to the image above for the location of the cable management 
bar.

  5.  Connect the included 5' 10" (1.78 m) power cable to the power jack on top of the 

power supply, and then connect the other end to a power source.

NOTE:

  Do not apply power until all modules have been installed and all 

connections have been made to the FT2-ELEC.

FT2-ELEC
power bus
barrel jacks

FT2 assembly
(bottom view)

Ground lug

Cable management bar

 

b. If connecting two power supplies to the power bus, connect each power supply’s 

power cord to a barrel jack in the power bus.

 

  Connecting the FT2A-UTK-PWS to the FT2-ELEC Power Bus

  3.  Slide the power supply into the power supply holder until it is secured in place.
  4.  Insert the power supply holder into the side of the FT2-ELEC assembly so that the 

four mounting posts on the rear of the holder engage the four rectangular slots in 
one of the six mounting locations. (Refer to the illustrations below.) Then, slide the 
holder downward until it is secured to the assembly.

 

Attaching the FT2A-UTK-PWS to the FT2-ELEC Assembly