Electrical Connection
21 / 79
Tools Required and Torque Values
No.
Tools
Usage
Torque value
1
No.2 Phillips head
screwdriver
DC Cable
3 N.m, 26.5 lbf-in
2
18mm hex socket
wrench
AC terminal block L1-L3 31 N.m, 274.4 lbf-in
3
10mm hex socket
wrench
External grounding
6 N.m, 53 lbf-in
4
5mm
flat
screwdriver
Internal grounding bar
3 N.m for terminal A
5 N.m for terminal B
5
1.5mm
flat
screwdriver
RS485 comm. terminal 0.2 N.m, 1.8 lbf-in
6
Diagonal pliers
Cut cable
-
7
Wire stripping pliers
Remove jacket
-
8
Crimping pliers
Crimp terminal
-
Table 4-2 Tools required and torque values
Connect Interfaces and Connection Points
In the following text, you will find the connect interfaces, internal connection points,
as well as their names, positions etc.
4.4.1
Connection Interfaces
The connection interfaces of inverter are as shown in figure 4-2.
Figure 4-2 Connection interfaces
No.
Item name
1
Knockouts for DC input
2
LINKIT interface
3
Communication interface
4
Knockout for AC output
5
External GND connection point
Table 4-3 Connection interfaces
Содержание SCH275KTL-DO/US-800
Страница 40: ...APP Interface 40 79 Figure 6 7 Protection Parameters ...
Страница 47: ...APP Interface 47 79 Others In the others interface you can find following common parameters shown as below ...
Страница 57: ...APP Interface 57 79 Figure 6 20 History interface 6 4 4 Turn ON OFF Figure 6 21 Turn ON OFF interface ...