12 of 64
CORRADI S.R.L.
- INSTALLATION MANUAL - PERGOTENDA ® MAESTRO
REV.1 - 11.2019
2 PILLAR INSTALLATION
Fig. 9
- Loosen the M8x16 BUTTON screw (
C
) and remove foot (
A
) from the pillar (
B
).
- The other 3 screws required for the next fixing operation are in the accessories box.
Note: perform this operation on all pillars of the structure.
Fig. 10
- Orient the pillar feet (
A
)
correctly and fix them to the ground using suitable dowels. In doing this,
respect the parallelism and diagonals referring to the 4 holes at the corners of the ground plate.
ATTENTION TO THE INSTALLATION: The foot sides with the holes for the pillar
retaining screws are those of side (PROJECTION). In case of floor water drain, before
fastening to the ground, trim the punched sticker with a cutter in the area of the drain hole
and apply a bead of silicone in the hole as shown in (Det. X)
.
A
B
C
A
A
A
A
Det. X
PROJEC
TION
WID
TH
IMPORTANT: the 4 pillars must be positioned so as to obtain a “PERFECTLY” flat structure; this is fundamental to ensure that rainwater correctly flows inside the pillars and does not spill over the
gutters.