M O N T H L Y P R E V E N T I V E M A I N T E N A N C E P R O C E D U R E S
Pin Chain Conveyor (Option) Lubrication
5-48
Bravo™ 8105 Preventive Maintenance Guide
Rev. 2
5
ATTENTION
Oil may be applied while processing boards, since the oil only touches the chain
and the chain tracks.
Photograph
Figure 5–7
Automatic Oiler
Operation
1. Load the oilers by lifting the oil fill cap at the top of the oiler reservoir and fill
with 10cc of oil. Do not overfill.
2. Adjust the oiler by turning the collar until oil drips at a rate of approximately
one (1) drip every ten (10) seconds.
3. Run the conveyor until the oil is gone (approximately 30 minutes).
4. Turn Off Oiler.