Technical Helpline: 0845 402 9924
SECTION A
Installing the pump
The 22mm flexible pipe supplied must be used from the 22mm outlet gully or waste to the pumps inlet.
Cut the flexible pipe to the required length. One end of the pipe has a grey solvent weld connector,
this must be solvent welded to the gully / waste outlet.
LEAVING EXCESS PIPE COILED BENEATH THE SHOWER TRAY WILL IMPEDE THE PUMPS
PERFORMANCE.
The maximum length of the flexible pipe between the waste and the pump should be no more than
2 metres
, with
as few, or no bends as possible.
Now connect the pump to the gully / waste
pipework using the flexible pipework kit supplied,
ensure both flexible pipes and jubilee clips are
attached.
FLUSH OUT PIPEWORK BEFORE MAKING FINAL
CONNECTION TO THE PUMP.
When level, mark holes and screw directly to the wall
using suitable fixings. Do not over tighten the screws.
Re-mount the pump to the bracket as previously described
in Points 2 & 2a.
The pump can be mounted horizontally, as shown, or
vertically without effecting performance.
Install the pump so that the outlet side of the pump is slightly higher than the soil pipe connection, this will
ensure a clean flow away from the pump, and help to keep the pipework clear.
If you want to use larger outlet pipework a suitable 22 - 40mm connector can be used.
ENSURE ALL PIPEWORK IS SECURELY FIXED TO THE WALL WITH SUITABLE PIPE CLIPS.
Do not leave excess pipe colied up beneath the shower tray.
Fit the pump within 2 metres of the gully or waste. To achieve
optimum
pump performance of
12 litres per minute we recommend the pump be installed no higher than
350mm
from the top
of the shower waste outlet to the underside of the wall plate, as shown in Point 3a .
The pump can be installed upto a maximum height of
500mm
but this
will
reduce the pump’s
overall performance.
See note 3a above if installing a Gannet top access shower tray.
Shower tray waste
Floor former waste
350mm
Recommended
Max 500mm
ENSURE ALL PIPEWORK CONNECTIONS ARE
SECURE TO AVOID ANY AIR BEING
SUCKED IN WHILST THE PUMP IS OPERATING.
THE PUMP
MUST NOT
BE FITTED IN THE
SHOWERING AREA.
ONCE THE INLET AND OUTLET DIRECTION HAS BEEN
ESTABLISHED THIS
SHOULD NOT
BE CHANGED.
1
1a
3
3a
4
5
6
!
!
!
!
Remove the pump from the wall bracket by undoing
the bolts on the top bracket, Point 2, and twisting the
inlet & outlet spigots anti-clockwise so the flanges
align with the slots in the wall bracket, Point 2a.
The pump body will now slide away from the wall
bracket.
2
2a
USE THE COLLAR PROVIDED TO PROTECT THE FLEXIBLE
PIPE WHEN DETAILING THE FLOOR COVERING.
!
IF INSTALLING A
GANNET
TRAY INSTALL THE PUMP
NO HIGHER THAN
350mm
FROM THE TRAY OUTLET
TO THE UNDERSIDE OF THE WALL PLATE.
!
USE THE WASTE / GULLY SUPPLIED.
CAN BE RETRO FITTED TO OTHER