Operation Manual
Track Supply 6 kW
80 / 125 A at 400 / 480 V
BAL9100-0124c-EN
www.conductix.com
Page 25 of 44
10.5
Electrical connection
10.5.1
Mains connection
The power cables of the supply lines L1, L2, L3 and PE have to be chosen as follows:
1.
Use only applicable cables that are approved according to VDE, UL or CUL.
2.
The Track Supply is designed for connection to a neutral grounded 3-phase supply system. While operation on alternative
supply systems such as corner grounded Delta maybe possible, it is unadvisable and may void the warranty. Please discuss
with Conductix-Wampfler if in doubt.
3.
The nominal voltage of the cables for systems of 480 V AC must be at least 600 V.
4.
The core cross-section has to be planned according to the relevant standards but recommended at least 2.5 mm².
5.
Grounding is to be realized according to VDE, NEC and IEC (see chapter 6.9 “Grounding”).
6.
The 3-phase input supply connection to X2 requires a flexible stranded core type cable for connection to the supplied Harting
connector. Maximum cable outer diameter is 18 mm with supplied PG 21 / M25 cable gland.
Attention!
To avoid damaging the input fuses we recommend that the 3-phase mains supply shall be only removed when the START / STOP-
signal is in the “STOP” position. A delay of at least 0.5 seconds is recommended!
min. 0.5 sec
Start / Stop
Control contactor
to mains