HCS QUAD PEDESTAL KIT INSTALLATION GUIDE
ClipperCreek
,
Inc.
Page 15
Figure 15: Mounting HCS EVSEs, Top Screws
Figure 16: Mounting HCS EVSEs, Bottom Screws
3. Connect the Wiring
The HCS has a flexible conduit extension with three
conductors. These conductors must be routed through
the side of the pedestal and the ninety-degree ½” NPT
fitting for connection.
• Locate the hole closest to the EVSE.
• Trim the EVSE conduit to length. The
recommended length of conduit to remain is
12
inches
as measured from the bottom of the EVSE.
• Route the three conductors that come through the
EVSE’s flexible conduit through the NPT
connection and pull through the top of the Pedestal
Post.
• No disassembly of the NPT Fitting is required.
Push the conduit onto the NPT Fitting ferrule and
then tighten the domed sealing nut on the NPT
fitting.
• For Quad-Mount Installations, repeat on the
opposite side.
• All sets of conductors and ground lug connections
inside the Pedestal Post must be pulled through
and connected at this time. The top access hole will
be blocked after this step.
Figure 17: Wiring and Conduit Placement
MOUNTING THE EVSES (continued)