37
FieldSmart
®
FiberFlex 2000
__________________________________________________________
Installation Manual
Direct: 763.476.6866 • National: 800.422.2537 • www.SeeClearfield.com • [email protected]
Manual 021574 REV A - June 2020
Preparing the Site
Excavate the pad area. Dig a foundation hole to the required depth (six inches deep minimum), with
a perimeter measuring at least 50 x 32 inches.
Grade and compact the excavated surface until it is firm and level.
Trench out conduit paths through the foundation hole from the cable feeder location.
Place the cable conduits into the conduit trench. Refer to the vault guidelines for conduit sizes and locations.
Route the earth ground wire through the conduit trench (from the ground electrode).
Place gravel into the foundation hole to create a level base. The gravel layer should be at least one inch deep,
compacted and leveled.
Step 1:
Step 2:
Step 3:
Step 4:
Step 5:
Step 6:
Prepare the site for installation of a foundation vault. Some vaults may require custom preparations. Refer to the
manufacturer’s instructions for more information.
A general practice is described below for reference. Adapt the instructions as needed for local requirements, practices, or
conditions.
To prepare the site for foundation vault installation