background image

w w w . c l a s s i c

e x h i b i t s . c o m

866.652.2100

© 2013

WHEN DISASSEMBLING ALUMINUM EXTRUSION, TIGHTEN ALL

SETSCREWS AND LOCKS TO PREVENT LOSS DURING SHIPPING

Order #XXXXX -  VK-1950 - Lightbox Assembly

Steps:

1) Attach lower vertical extrusions [2,3] to base plates [1] using screws.

2) Attach upper vertical extrusions [2a,3a] to lower vertical extrusions [2,3] as shown in detail.

3) Connect curved horizontals [4,4a,5,5a] together as shown.

4) Attach horizontal assemblies between vertical assemblies [2/2a,3/3a] as shown.

5) Apply blocker fabric to 

velcro 

on outside of horizontals [5/5a) and verticals.

6) Attach SuperNova light to verticals [2/2a,3/3a] and horizontals [5,5a] as shown, 

  connecting connectors together. 

7) Attach SEG graphics to front SEG groove according to detail below.

8) Attach wings to A-10 clamps as shown.

Item  Qty Description

Base Plate

2/2a 

1/1  45” Half Round Vertical Extrusion

3/3a 

1/1  45” Half Round Vertical Extrusion

4/4a  2/2   44.5041” Z45 Horizontal Extrusion

5/5a 

2/2  46.6892” Z45 Curved Horizontal Extrusion

Velcro:

Outside/Bottom Edge

Velcro:

Back 

Outside

Edge

Velcro:

Outside/Top Edge

**

Note:

 the opening

of 

SEG 

extrusions must 

be positioned outward 

from the light box.

1

1

2

2a

3

3a

4

4

4a

4a

5

5

5a

5a

*

*

*

Screws

Graphic Removal

To  remove  the  graphic from

the  frame,  locate  the  fabric 

pull tab.  Gently pull up on the 

tab to remove the fabric.

Step 1

Insert corner A.  Turn edge of 

graphic  so  silicon  welt  is 

perpendicular  to  face  of 

graphic.  Insert  narrow  side 

of welt with fabric to outside 

into the channel.  Repeat for 

other side of this corner.

Step 2

Repeat  Step  1  for  opposite 

corner C, then insert corner 

B,  followed  by  corner  D,  to 

complete  the  installation  of 

the corners.

Step 3

Once all corners are inserted, 

press  one  silicon  edge  into 

channel  from  corners  and 

work  toward  the  center.  

Make sure welt is fully inserted 

into channel.  Continue until 

all  sides  are  done.  Smooth 

out edges of graphic.

Graphic: To Ensure Proper Fit

It  is  important  to  first  insert 

graphic  into  each  alternate 

corner  then  to  the  sides  of 

the frame.  If this is not done, 

graphic  will  not  fit  into  the 

frame correctly.

Corner A

Corner D

Corner B

Corner C

SuperNova Lights:

Attach to inside of verticals [2/2a,3/3a]

and top of curved horizontals [5]

Velcro:

Back 

Outside

Edge

SuperNova Lights:

Attach to inside of verticals [2/2a,3/3a]

and bottom of curved horizontals [5a]

Tighten set screw to

secure A10 to extrusion.

A10 Clamp Detail

Tighten knob to secure

header/wing in place.

Отзывы: