Cisco ONS 15454 Procedure Guide, R5.0
March 2005
Chapter 17 DLPs A1 to A99
DLP-A23 Install DS-1 Cables Using Electrical Interface Adapters (Balun)
Step 3
Return to your originating procedure (NTP).
DLP-A23 Install DS-1 Cables Using Electrical Interface Adapters (Balun)
Note
All DS-1 cables connected to the ONS 15454 DS-1 ports must terminate with twisted-pair cables to
connect to the DS-1 electrical interface adapter. The DS-1 electrical interface adapters project
1.72 inches (43.7 mm) beyond the SMB EIA. Refer to the “Shelf and Backplane Hardware” chapter in
the
Cisco ONS 15454 Reference Manual
for more information.
Step 1
Attach the SMB connector on an adapter to the SMB connector for the port’s transmit pair on the
backplane.
Step 2
Attach the SMB connector on an adapter to the SMB connector for the port’s receive pair on the
backplane.
Step 3
Terminate the DS-1 transmit and receive cables for the port to the wire-wrap posts on the adapter:
a.
Using a wire-wrap tool, connect the receive cables to the receive adapter pins on the backplane
connector for the desired port.
b.
Connect the transmit cables to the transmit adapter pins on the backplane connector for the desired
port.
c.
Terminate the shield ground wire on the DS-1 cable to ground according to local site practice.
Note
If you put DS1N-14 cards in Slots 3 and 15 to form 1:N protection groups, do not wire Slots 3
and 15 for DS-1 electrical interface adapters.
shows a ONS 15454 backplane with an SMB EIA. DS-1 electrical interface adapters are
attached on both sides of the shelf assembly to create DS-1 twisted-pair termination points.
Purpose
This task installs the DS-1 cables on an SMB EIA using the electrical
interface adapters.
Tools/Equipment
Wire wrapper
Twisted-pair cables
Prerequisite Procedures
DLP-A13 Install an SMB EIA, page 17-15
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
None
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...