Create Circuits and VT Tunnels
Note
The terms “Unidirectional Path Switched Ring” and “UPSR” may appear in Cisco literature. These terms
do not refer to using Cisco ONS 15xxx products in a unidirectional path switched ring configuration.
Rather, these terms, as well as “Path Protected Mesh Network” and “PPMN,” refer generally to Cisco’s
path protection feature, which may be used in any topological network configuration. Cisco does not
recommend using its path protection feature in any particular topological network configuration.
This chapter explains how to create Cisco ONS 15454 electrical circuits, tunnels, OC-N circuits,
Ethernet circuits, and virtual concatenated (VCAT) circuits. For additional information about
ONS 15454 circuits, refer to the “Circuits and Tunnels” chapter in the
Cisco ONS 15454 Reference
Manual
.
Before You Begin
Before performing any of the following procedures, investigate all alarms and clear any trouble
conditions. Refer to the
Cisco ONS 15454 Troubleshooting Guide
as necessary.
This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).
1.
NTP-A127 Verify Network Turn Up, page 6-4
—Complete this procedure before you create any
circuits.
2.
NTP-A181 Create an Automatically Routed DS-1 Circuit, page 6-6
—Complete as needed.
3.
NTP-A182 Create a Manually Routed DS-1 Circuit, page 6-11
—Complete as needed.
4.
NTP-A183 Create a Unidirectional DS-1 Circuit with Multiple Drops, page 6-14
—Complete as
needed.
5.
NTP-A184 Create an Automatically Routed DS-3 Circuit, page 6-18
—Complete as needed.
6.
NTP-A185 Create a Manually Routed DS-3 Circuit, page 6-23
—Complete as needed.
7.
NTP-A186 Create a Unidirectional DS-3 Circuit with Multiple Drops, page 6-25
—Complete as
needed.
8.
NTP-A133 Create an Automatically Routed VT Tunnel, page 6-29
—Complete as needed.
9.
NTP-A134 Create a Manually Routed VT Tunnel, page 6-31
—Complete as needed.
10.
NTP-A187 Create a VT Aggregation Point, page 6-33
—Complete as needed.
11.
NTP-A135 Test Electrical Circuits, page 6-36
—Complete this procedure after you create an
electrical circuit.
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...