Cisco ONS 15454 SDH Procedure Guide, R7.0
78-17194-01
Chapter 17 DLPs D1 to D99
DLP- D6 Mount the Shelf Assembly in a Rack (Two People)
DLP-D6 Mount the Shelf Assembly in a Rack (Two People)
Note
The ONS 15454 SDH requires 616.5 mm (24.24 inch) minimum of vertical rack space and 25 mm
(1 inch) below the installed shelf assembly to allow air flow to the fan intake. If a second
ONS 15454 SDH is installed above a shelf assembly, the air ramp between the shelves provides space
for air flow. To ensure the mounting is secure, use two to four M6 mounting screws for each side of the
shelf assembly. A shelf assembly should be mounted at the bottom of the rack if it is the only unit in the
rack.
Step 1
Verify that the chassis fuses rating does not exceed 30A.
Step 2
Ensure that the shelf assembly is set for the desired rack size.
Step 3
Using the hex tool that shipped with the assembly, install the temporary set screws into the holes that
will not be used to mount the shelf. Let the screws protrude sufficiently to hold the mounting brackets.
Step 4
Lift the shelf assembly to the desired position in the rack.
Step 5
Align the screw holes on the mounting bracket with the mounting holes in the rack.
Step 6
Have one person hold the shelf assembly in place while the other person installs one mounting screw in
each side of the assembly using the Phillips screwdriver.
Step 7
When the shelf assembly is secured to the rack, install the remaining mounting screws.
Note
Use at least one set of the horizontal screw slots on the ONS 15454 SDH to prevent slippage.
Step 8
Using the hex tool, remove the temporary set screws.
Step 9
Return to your originating procedure (NTP).
Purpose
This task allows two people to mount the shelf assembly in a rack.
Tools/Equipment
Pinned hex tool
Two M6 x 20 socket set screws
Eight M6 x 20 mm pan-head Phillips mounting screws
#2 Phillips screwdriver
Prerequisite Procedures
NTP-D1 Unpack and Inspect the ONS 15454 SDH Shelf Assembly, page
1-4
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
None
Содержание ONS 15454 SDH
Страница 26: ...Tables vi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 ...
Страница 62: ...xxii Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 64: ...xxiv Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 66: ...xxvi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 414: ...16 4 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Chapter 16 Power Down the Node NTP D114 Power Down the Node ...
Страница 832: ...A 14 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 860: ...Index IN 28 Cisco ONS 15454 SDH Procedure Guide R6 0 78 17194 01 ...