DLP-G575 Turn On and Verify DC Office Power on the ONS 15454 M6 Shelf
This task turns on the power and verifies correct power and returns on the ONS
15454 M6 shelf.
Purpose
Voltmeter
Tools/Equipment
•
NTP-G252 Install the ONS 15454 M6 Shelf , on page 24
.
•
NTP-G259 Open and Remove the Standard Door of the ONS 15454 M6
Shelf , on page 57
• Connect the chassis to the office ground. For detailed instructions on how
to ground the chassis, see the
Electrostatic Discharge and Grounding Guide
for Cisco CPT and Cisco ONS Platforms
•
NTP-G524 Install the Power Modules in the ONS 15454 M6 Shelf , on page
85
.
•
DLP-G572 Connect Office Power (DC) to the ONS 15454 M6 Shelf (ANSI
Only), on page 107
•
DLP-G573 Connect Office Power (DC) to the ONS 15454 M6 Shelf (ETSI
Only), on page 111
Prerequisite Procedures
Required
Required/As Needed
Onsite
Onsite/Remote
None
Security Level
Do not apply power to the shelf until you complete all the installation steps.
Caution
To ensure safety of personnel and equipment, do not connect any power cables into the power module
until the module is completely installed into the chassis.
Statement 389
Warning
To reduce the risk of electric shock, switch on the power only after the power cord is completely installed
into the power module.
Statement 390
Warning
Procedure
Step 1
Using a voltmeter, verify the office battery and ground at the following points on the fuse and alarm panel:
a) To verify the power, place the black test lead of the voltmeter to the frame ground. Place the red test lead
on the A-side connection and verify that it is between –40.5 VDC and –72.0 VDC. Place the red test lead
on the B-side connection and verify that it is between –40.5 VDC and –72.0 VDC.
Installing the ONS 15454 M6 Shelf
116
Installing the ONS 15454 M6 Shelf
DLP-G575 Turn On and Verify DC Office Power on the ONS 15454 M6 Shelf