Cisco ONS 15454 DWDM Procedure Guide, R8.0
78-17704-02
Chapter 1 Install the Shelf and Common Control Cards
NTP- G17 Connect Office Power to the ONS 15454 ETSI
DLP-G17 Connect Office Power to the ONS 15454 ETSI
Warning
When installing or replacing the unit, the ground connection must always be made first and
disconnected last.
Statement 1046
Caution
Do not apply power to the ONS 15454 ETSI until you complete all installation steps and check the
continuity of the –48 VDC battery and battery return.
Note
Not more than 2 m (7 ft) of the power supply cable should be exposed between the equipment and the
fiber-storage tray.
Note
Only use listed compression-type connectors when terminating the battery, battery return, and ground
conductors. Connectors must be suitable for copper conductors.
Caution
When terminating power, return, and frame ground, do not use soldering lug connectors, screwless
(push-in) connectors, quick-connect connectors, or other friction-fit connectors.
Purpose
This task connects power to the ONS 15454 ETSI shelf.
Tools/Equipment
#2 Phillips Dynamometric screwdriver
Medium slot-head screwdriver
Small slot-head screwdriver
Wire wrapper
Wire cutters
Wire strippers
Crimp tool
Fuse panel
Power cable (from fuse and alarm panel to assembly), 5.26-mm²
(#10 AWG), copper conductors, 194 degrees F [90 degrees C])
Ground cable 13.3-mm² (#6 AWG) stranded
Listed pressure terminal connectors such as ring and fork types; connectors
must be suitable for 5.26-mm² (#10 AWG) copper conductors
Prerequisite Procedures
DLP-G15 Connect the Office Ground to the ONS 15454 ETSI, page 1-34
Required/As Needed
Required
Onsite/Remote
Onsite
Security Level
None