Cisco 12010, Cisco 12410, and Cisco 12810 Router Installation and Configuration Guide
OL-11496-01
Chapter 7 Maintaining the Router
Removing and Replacing AC and DC Power Subsystem Components
Step 12
Reconnect the 2800 W DC power cables in the following order (
a.
Ground cables first.
b.
Positive cables next.
c.
Negative cable last.
d.
Repeat steps a, b, and c for the other PDU.
e.
Go to
.
Warning
To prevent injury and damage to the equipment, always attach the ground and
source DC power cable lugs to the power shelf terminals in the following order:
(1) ground to ground, (2) positive (+) to positive (+), (3) negative (–) to
negative (–).