Chapter 7 Maintaining the Router
Powering Off the Router
7-2
Cisco 12010, Cisco 12410, and Cisco 12810 Router Installation and Configuration Guide
OL-11496-01
Prerequisites and Preparation
Before you perform any of the procedures in this chapter, be sure that you:
•
Review the
“Safety Guidelines” section on page 2-2
•
Read the safety and ESD-prevention guidelines described in the
and Safety Information” section on page 2-3
.
•
Ensure that you have all of the necessary tools and equipment before
beginning the procedure.
•
Have access to the following documents during the installation:
–
Regulatory Compliance and Safety Information for Cisco 12000 Series
Routers
publication that shipped with the router (PN 78-4347-xx)
Powering Off the Router
Most Cisco 12010, Cisco 12410, and Cisco 12810 series routers field-replaceable
units (FRUs) can be removed and replaced with the power on and the system
operating. This is known as online insertion and removal (OIR). Power supplies,
line cards, the RP, CSCs, SFCs, and alarm cards all support OIR. Unless otherwise
noted, the maintenance tasks described in this chapter can be performed while the
router remains powered on.
In some cases it may be necessary to power off the router, for example, to upgrade
both power supplies and PDUs. Use the following procedure to power off the
router.
Step 1
Set the power switch on each power supply to the off (0) position.
Step 2
Power off all circuit breakers for the source power lines connected to the power
supplies.
Step 3
Verify that the Pwr OK indicator on each power supply is off.
Step 4
Verify that the OK indicator on the blower module is off.
Содержание 12010 series
Страница 6: ......
Страница 363: ...B 3 Cisco 12010 Cisco 12410 and Cisco 12810 Router Installation and Configuration Guide OL 11496 01 Appendix B Site Log ...
Страница 364: ...Appendix B Site Log B 4 Cisco 12010 Cisco 12410 and Cisco 12810 Router Installation and Configuration Guide OL 11496 01 ...