1.  Remove old packing from stuffing box. Stuffing box should 

be free of any old packing residue, solids and corrosion left 

from the process.

2.  Inspect pump sleeve. Sleeve should be in good condition 

and free of excessive wear, corrosion or pitting for optimum 

packing service life.

3.  Clean the packing gland and gland follower. Remove burrs, 

corrosion or any residual material which would impede 

insertion into the stuffing box.

4.  Calculate the packing cross section:

a.  Measure the shaft sleeve diameter (or locate and  

measure a packing mandrel, an old packing sleeve or  

a piece of wood the same diameter as the shaft sleeve).

b.  Measure the stuffing box bore.
c.  Cross section = (Bore ID – Stem OD) ÷ 2.

5.  Wrap the packing around the packing mandrel and mark at 

one complete ring.

6.  Remove packing from mandrel.
7.  Before cutting rings determine which style packing you 

want facing the shaft, then cut rings using a 45° skive cut.

8.  Each ring should be cut with the arrangement required for 

each application. Typical arrangement would be (3) primary 

sealer rings (shown in Figure 1 with Black ePTFE facing the 

shaft), (1) top end ring, and (1) bottom end ring (shown in 

Figure 2).

(See Figure 3 for stuffing box arrangement)

Additional rings may be required to pack the stuffing box.  After 

each ring is cut wrap them around mandrel to check fit before 

proceeding to installation.

DualPac

 2211

Installation Instructions

EQUIPMENT PREPARATION

MECHANICAL PACKING  

INSTALLATION INSTRUCTIONS

CAUTIONS

These instructions are general in nature. It is assumed that the installer 

is familiar with mechanical packing and with the plant requirements for 

the successful use of mechanical packing. If in doubt, get assistance 

from someone in the plant that is familiar with the product, or delay the 

installation until a packing representative is available. 

All necessary auxiliary arrangements for successful operation 

(heating, cooling, flushing) as well as safety devices must be 

employed. These decisions are to be made by the user.  

The decision to use this or any other Chesterton product in  

a particular service is the customer’s responsibility.

Black ePTFE

Yellow Aramid

Figure 1 – Primary Sealer 

(SHOWN WITH Black ePTFE SEALING SHAFT)

  Figure 2 – End Ring